Read 22 min

How Foremen Prepare for Pull Planning and Pre-Construction Meetings

If you study the root cause of most constraints and roadblocks that stop the train of trades on a construction project, two events come up over and over. Not the weather. Not the material delays. Not the inspectors. The pull plan that was not done properly, and the pre-construction meeting that was not done properly. Those two events or the failure of them account for the overwhelming majority of the problems that show up in the field as surprises.

The uncomfortable part is that these are also the two meetings most people least want to attend. Pull planning is hard, time-consuming, and requires foremen and trade partners to give production information and commit to sequences months before the work starts. The precon meeting feels boring and procedural until the first time a trade enters a zone without one and spends three days figuring out what should have been figured out before they touched a tool. The field is for installing, not for figuring things out. The pull plan and the precon meeting are where the figuring out happens. And if they do not happen correctly, the field pays for it every time.

The Pull Plan: Starting Four Months Before the Phase

A pull plan should happen three months before the phase starts. That means the first contact with trade partners the reach-out to invite participation and gather the homework that makes the pull plan useful needs to happen four months before the phase. Not three. Four. The homework gives the project delivery team the production information they need to pre-analyze bottlenecks and solve system constraints before everyone sits down together. Waiting until the pull plan session itself to discover that a trade has a significantly different production rate than the schedule assumed is too late.

The homework ask is specific: here are the key features of the pull plan session, here is the detailed information about the phase, and here is what we call the Lego brick sheet a request for each trade’s detailed production information for their fastest, median, and slowest speed for their activities in this phase. That information lets the project delivery team identify potential bottlenecks before the pull plan and address them in the session rather than discovering them after the phase has started.

Trade participation at this stage is not optional. It is the first indicator of how a trade partner will behave for the rest of the project. A trade that cannot be reached four months before their phase starts, or that does not respond to a reasonable and clearly communicated request for production information, is showing the team exactly what the working relationship is going to look like once they are in the zone. Not because the foremen do not care in most cases the communication broke down somewhere or the process is new and unfamiliar but because total participation requires engagement from the very beginning, and the pull plan is the beginning.

What Happens Inside the Pull Plan

The pull plan is a collaborative sequence-building session. The team starts by working forward through one zone establishing the sequence of activities, the predecessors, and the handoffs between trades for that zone. Then they work backwards through the same zone to confirm that every trade has what they need: the information, the access, the predecessors, the materials, and the conditions of satisfaction that allow them to start and finish. Then the sequence is cascaded from zone to zone to zone, and the diagonal trade flow is analyzed to confirm that every trade can move continuously from one zone to the next without gaps or stacking.

The pull plan is answering two questions simultaneously: what does the project need, and what does the trade need? Both answers matter equally. The project needs the sequence to produce a milestone. The trade needs the conditions to produce the work. The pull plan is the conversation where both get addressed in partnership rather than one side forcing their answer on the other.

After the pull plan, the sequence and the production information go into the project management software as the norm-level Takt production plan. That plan is not a starting point for more planning work. It is the foundation from which the look-ahead and the weekly work plan are filtered not created fresh, filtered. A trade partner who has been through pull planning on a CPM-based Last Planner site knows exactly how much time gets wasted creating the same plan over and over at every planning horizon. In the Takt system, the pull plan is done once, correctly, with the trades, and everything that follows is a filter from that collaborative agreement.

The Pre-Construction Meeting: Three Weeks Before Each Wagon

After the pull plan establishes the production plan, the pre-construction meeting happens three weeks before each trade’s first wagon enters the zone. One precon for each wagon in the train. Not one precon for the whole phase. Not a meeting at the beginning of the project that is supposed to cover everything a trade will ever need. A targeted precon, three weeks before each wagon’s start, specifically focused on making that trade ready to hit the ground running when their zone opens.

The precon meeting covers the production plan in the context of the trade’s specific scope, the logistics plan, the zone maps, and the construction work areas the trade will be working in. It is where the project delivery team and the trade partner together look at the work and ask: is this what you need? Is this what the owner needs? If we do this, is this what you want? The questions, the answers, and the adjustments that come out of that conversation are what create alignment before the work starts rather than during it.

The most important output of the precon meeting is the installation work package specifically, the feature of work board. This is a highly visual set of instructions: the standard work for the scope being installed in this work package, shown in a format that can be printed and taken out to the crew board in the field. The dos and the don’ts. The quality standard. The safety requirements. The specific details that the first-in-place inspection will be checking. It is created collaboratively in the precon with the foreman’s input, which means it reflects how the work will actually be done rather than how someone in the office imagined it would be done. And it goes on the crew board so the workers have it where the work is happening, not in a Procore log that requires a login to access.

Full Kit Before the First Zone

The principle that governs everything in the precon meeting is full kit. Do not start until you are ready to finish. Not ready to start ready to finish. The labor confirmed and ramped. The materials on site or confirmed inbound on a specific date. The equipment staged and available. The permissions in hand. The information resolved. The layout completed. The space cleared and accessible. Every condition the trade needs to move from the first zone to the last zone without a stop-and-restart confirmed before the first zone opens.

“Let’s just go get started and see how it goes” is not a production strategy. It is a decision to send the trade into the field to figure out things that should have been figured out in the precon meeting, which means the field absorbs the cost of that figuring out in productivity lost, time wasted, and frustration built between the GC and the trade partner. The field is for installing. The precon meeting is where everything that would otherwise interrupt the installation gets identified, discussed, and resolved. A foreman who walks out of the precon meeting with a complete installation work package, a feature of work board, a clear picture of the zone map, and confirmation that the full kit will be in place three weeks later is a foreman who can lead the crew with confidence from the first day in the zone.

Warning Signs That Pull Planning and Precon Meetings Are Not Working

Before the field absorbs the cost of inadequate preparation, watch for these signals:

  • Trade partners have not responded to the homework request four months before their phase and nobody has followed up to understand why or fix the communication breakdown.
  • The pull plan session happens but the zone analysis was not done beforehand, so the team is discovering the right zone sizes during the session rather than proposing them from a completed analysis.
  • Pre-construction meetings are happening once for the whole phase rather than three weeks before each wagon, which means later wagons are entering zones without a current precon that reflects actual conditions.
  • The feature of work board does not exist for critical work packages, so the first-in-place inspection has no visual reference and the quality standard is being communicated verbally and inconsistently.
  • The look-ahead and weekly work plans are being created from scratch each week rather than filtered from the norm-level production plan that the pull plan produced.

Every one of those signals is the same root cause: the two most important preparation events the pull plan and the precon meeting did not happen in a way that actually prepared the field for what was coming.

We are building people who build things. The foremen who give their full participation to the pull plan and the precon meeting who bring their production information, engage with the sequence, contribute to the installation work package, and enter their first zone with full kit confirmed are the foremen who lead crews that flow. If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow including the pull planning and precon meeting discipline that gets every trade to their first zone ready to finish, not just ready to start.

A Challenge for Builders

On your current project, identify the next trade that is three to four months away from their phase start. Has the homework request been sent? Does that trade know what the pull plan session will ask of them, and do they have the production information needed to participate meaningfully? If the answer to either question is no, send the reach-out this week. The pull plan is the most important thing that happens before a trade enters a zone. Four months is the preparation that makes it work. Start the clock now.

As Jason says, “Plan it first, build it right, finish as you go.”

On we go.

Frequently Asked Questions

Why must the pull plan homework go out four months before the phase start if the pull plan itself is three months out?

Because the homework asks for detailed production information fastest, median, and slowest speeds for each activity that requires time to gather and analyze. With that information in hand a month before the pull plan session, the project delivery team can pre-analyze bottlenecks, identify system constraints, and propose solutions before everyone sits down together. Discovering those constraints in the pull plan session is manageable. Discovering them in the field is expensive.

What is a feature of work board and why does it matter?

A feature of work board is the visual output of the precon meeting a printed, highly visual set of installation instructions that shows the standard work for a specific scope of work, the dos and the don’ts, the quality requirements, and the safety requirements. It goes on the crew board so the workers have it at the workface where the installation is happening. It is also the reference standard for the first-in-place inspection, so the quality standard is agreed upon visually before the first installation rather than argued about after it.

What does “full kit” mean and why is it the governing principle of the precon meeting?

Full kit means every condition a trade needs to start and finish their scope in the zone is confirmed to be in place before the first zone opens: labor committed and ramped, materials on site or confirmed inbound, equipment staged, permissions in hand, information resolved, layout completed, space cleared. The precon meeting is where the team works through the full kit checklist together and confirms or plans for every item. Starting without full kit means sending the trade into the field to figure out what the precon should have resolved which costs time, productivity, and the working relationship between the GC and the trade partner.

If you want to learn more we have:

-Takt Virtual Training: (Click here)
-Check out our Youtube channel for more info: (Click here) 
-Listen to the Elevate Construction podcast: (Click here) 
-Check out our training programs and certifications: (Click here)
-The Takt Book: (Click here)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction IST. As the company’s owner and principal consultant, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.