The final steps in the field engineering or builder’s role bring everything together. By this point, the foundation is strong, the drawings are ready, and the field is active. Now it becomes about quality, coordination, and building habits that ensure success as projects move forward.
Step 30 is where the port check process begins. With primary, secondary, and working control already in place, the project is likely in full motion. This is when quality checks come into play. Whether it is verifying masonry walls, checking a concrete placement, or performing general QC, this is where the builder shifts into a rhythm. The process should always follow a cycle of plan, build, and finish. Running around without focus leads to mistakes. Instead, the role of the field engineer is to plan each task, help the crew build it correctly, and then confirm the work is finished according to standards.
Step 31 builds on this by creating quality checklists. These checklists come directly from preconstruction meetings and ensure that nothing is overlooked. They keep teams aligned on expectations and provide accountability for installation standards.
Step 32 introduces features of work boards. Not every task falls into the typical categories of concrete or masonry. For unique scopes like installing an underground tank, visual feature of work boards make a big difference. These boards combine pictures from manufacturer instructions, bullet lists of steps, and clear visuals for the install teams. Whether it is a checklist or a feature of the work board, the point is the same: crews need clarity, and visual communication makes quality repeatable.
Step 33 emphasizes the importance of Revit. While ideally this tool is set up earlier in the process, now is the point where it becomes essential. Revit enables the creation of lift drawings, which are the foundation for field checks and planning. Installing the software, learning the basics, and setting it up properly is a non-negotiable skill for a builder. Training resources are available through platforms like LinkedIn Learning or internal company libraries.
Step 34 is where the first lift drawing comes to life. This drawing must meet lift drawing requirements and be thoroughly checked. Foremen and lead engineers should review it deeply. If it does not come back covered in red notes, the review is not detailed enough. These drawings become living documents that guide construction in the field, so creating them quickly and aligning them with the schedule is key.
Step 35 focuses on writing the first RFI. While project engineers or office engineers may handle this, field engineers benefit from owning the process. Writing RFIs connects directly to the work being installed and builds a deeper understanding of details, requirements, and potential gaps. This habit creates ownership and strengthens communication between the field and the design team.
Step 36 introduces the first trend chart. Tracking production in real time allows superintendents to see progress clearly. Whether it is cubic yards of concrete placed or the volume of excavation completed, data visualized in a chart gives insight into performance. This is a practice every builder should learn, as it strengthens accountability and supports proactive decision-making.
Step 37 shifts focus to vertical control. Once the project goes vertical, it is necessary to design methods for transferring grid lines and elevations from one level to the next. Options include chaining up from tower cranes, using vertical columns, or placing sleeves in decks for layout. This step requires planning, because mistakes at this stage can multiply across multiple floors. Lean survey resources and field engineering manuals provide excellent guidance on how to get this right.
Step 38 expands vertical control into transferring elevations. If elevations are not carried correctly from floor to floor, alignment problems can spread throughout the building. Careful planning and proper methods are critical to avoiding errors that can cost significant time and money.
Step 39 completes the sequence with grid leveling of structural decks. After placements, it is essential to check the floor flatness and document results. Without this step, teams risk needing expensive floor floating later in the project, which can run into hundreds of thousands of dollars. Getting it right the first time is the most cost-effective and efficient approach.
Together, these final steps complete the builder’s sequence. They provide a roadmap for quality, accountability, and consistency in the field. With port checks, checklists, lift drawings, RFIs, trend charts, and vertical controls in place, the builder’s role transitions from setting up systems to maintaining them as construction accelerates upward.
This closes out the field engineering series. These steps will be compiled into a guidebook tied to the field engineering methods manual so teams can use it as a reference. With this foundation, field engineers can approach their work with clarity, confidence, and consistency, helping their projects run smoother and their teams succeed.
Key Takeaway
The final steps of field engineering are about quality, clarity, and control. With proper planning and discipline, builders can ensure consistency as projects rise vertically and gain momentum.
If you want to learn more we have:
-Takt Virtual Training: (Click here)
-Check out our YouTube channel for more info: (Click here)
-Listen to the Elevate Construction podcast: (Click here)
-Check out our training programs and certifications: (Click here)
-The Takt Book: (Click here)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction IST. As the company’s owner and principal consultant, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.
On we go