First Run Studies: The Lean Way to Build It Right the First Time
One of the most common questions I get from superintendents, project managers, and executives is simple, honest, and frustratingly universal. Why do we always lose time at the start? Why does the job feel chaotic before it ever feels stable? Why do crews struggle early and only find their rhythm after the damage is already done?
If you have ever stood on a jobsite watching a trade rush, panic, and push materials before they are ready, you already know the answer in your gut. We start work before we are ready to finish it.
That is exactly where first run studies come in. Not as a buzzword. Not as a classroom exercise. But as one of the most practical, respectful, and powerful Lean tools we have in construction.
The Pain We All Feel at the Start of Work
Every project begins with pressure. Schedules are tight. Owners are watching. Teams feel the weight to move fast. And so we do what construction has always done. We start.
Crews mobilize before they fully understand the work. Materials arrive early or late. Tools are missing. Information is incomplete. Supervision is stretched thin. The first zones become learning zones, and the project absorbs the cost of that learning in the most expensive way possible.
We accept this pain as normal. We even joke about it. But deep down, everyone knows it is avoidable.
The Failure Pattern That Slows Projects Down
The failure pattern is not laziness or incompetence. It is starting without full kit and hoping experience will save us.
When crews rush without clarity, quality suffers. When quality suffers, flow collapses. When flow collapses, buffers get eaten. And once buffers are gone, the project lives in recovery mode.
I have watched this pattern repeat itself hundreds of times, both in the field and in simulations. Speed without preparation always loses.
What Simulations Taught Me About Quality and Flow
Years ago, I was introduced to a 3D printed building simulation developed by experts in Takt planning. It looks simple on the surface. Plastic pieces. Trades moving through zones. A clock running.
The first time teams run the simulation, they rush. They push materials. They overlap work. They panic when bottlenecks appear. Completion times land somewhere between ten and twenty minutes.
Then something interesting happens. When teams slow down, study the work, right size zones, and implement Takt and Last Planner, the times drop dramatically. I have seen teams complete the same scope in under four minutes.
What made the difference was not working harder. It was quality.
Teams that refused to start work until they knew they could finish it within the Takt time consistently outperformed everyone else. Quality became the differentiator.
The Emotional Insight Behind First Run Studies
This is where Lean becomes human.
Crews do not want to fail. Trades do not want to look bad. When we throw them into work without preparation, we force them into survival mode. They rush because they feel unsafe. They push because they feel pressure. They make mistakes because the system set them up to do so.
First run studies are an act of respect. They say, we care enough about you, the project, and the outcome to get this right before it matters most.
First Run Studies and the Idea of Full Kit
The concept behind first run studies comes straight from the rules of flow. Full kit means having everything required to finish a task before starting it. That includes information, materials, tools, equipment, trained people, and clear expectations.
A first run study is how we verify full kit in the real world.
It is not about perfection. It is about learning in the safest, cheapest, and most respectful environment possible before the project depends on it.
How First Run Studies Actually Happen in Construction
First run studies do not require tearing work out and rebuilding it. They show up in construction more often than people realize.
One approach is observing the first zone on your own project. The trade enters with full kit, and supervision stays close. The team learns, adjusts, and improves. This is helpful, but it comes at the cost of lost time in that first zone.
A better approach is studying the same crew doing the same work on a previous project. Great superintendents visit other sites. They watch installations. They time the work. They ask questions. When that crew arrives, the learning curve is already behind them.
Another powerful option is a mockup. I learned this lesson the hard way early in my career on a highly complex exterior system. The mockup took three times longer than planned. I trusted the trade when they said it would go faster on the building. It did not. The mockup was telling us the truth, and we failed to listen.
Mockups are first run studies with teeth. They reveal reality without risking the project.
Why Preparation Beats Pushing Every Time
One pattern shows up consistently in both simulations and real projects. Teams that rush spiral. Teams that prepare accelerate.
When trades refuse to start work until they know they can finish it within the Takt time, the results are dramatic. Buffers stay intact. Quality stays high. Morale improves. Flow stabilizes.
This is why LeanTakt planning emphasizes readiness over activity. Motion without readiness is waste. Preparation creates speed.
What First Run Studies Make Visible
When first run studies are done well, they expose truths that would otherwise surface too late.
- Installation times that do not match assumptions
- Missing information or unclear details
- Training gaps within crews
- Material or tool constraints that limit flow
None of these are failures. They are gifts, if discovered early.
Connecting First Run Studies to Trade Partnership
One of the biggest shifts I have seen in high performing projects is how leaders spend their time. In world class manufacturing, leaders spend most of their time with vendors. In construction, our vendors are our trades.
If we expect flow, we must prepare together.
Spending time with trades before they mobilize, observing their work, and helping them succeed is not micromanagement. It is leadership.
Practical Guidance Without the Checklist Mentality
The goal of a first run study is not to document everything. It is to learn enough to protect the project.
Sometimes that learning comes from a mockup. Sometimes from a site visit. Sometimes from a first in place inspection. The method matters less than the intent.
The intent is always the same. Do not start what you are not ready to finish.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
How This Aligns with Elevate Construction’s Mission
At Elevate Construction, we believe remarkable projects are built by systems that respect people. First run studies embody that belief. They reduce chaos. They protect dignity. They create flow.
They also align perfectly with LeanTakt principles, where stability comes before speed and quality comes before output.
Conclusion: Build It Right the First Time
First run studies are not about slowing down. They are about going faster for longer.
When we invest time upfront to learn, prepare, and align, the project stops fighting us. Crews gain confidence. Leaders regain control. Flow becomes predictable.
The challenge is simple. Before your next major scope starts, ask yourself one question. Are we truly ready to finish this, or are we hoping experience will save us?
As I often say, hope is not a strategy.
And as W. Edwards Deming reminded us, “Quality comes not from inspection, but from improvement of the process.”
On we go.
Frequently Asked Questions
What is a first run study in construction?
A first run study is a focused effort to understand how work will actually be performed before full production begins, ensuring quality and readiness.
How does a first run study support LeanTakt?
It verifies full kit and supports stable Takt flow by preventing early bottlenecks and rework.
Are mockups considered first run studies?
Yes. Mockups are one of the most powerful forms of first run studies because they reveal real installation challenges early.
Can first run studies be done without slowing the project?
Yes. When done early and intentionally, they save far more time than they consume.
Who should be involved in a first run study?
Field leaders, trades, and support staff should all participate to ensure learning is shared and applied consistently.
If you want to learn more we have:
-Takt Virtual Training: (Click here)
-Check out our Youtube channel for more info: (Click here)
-Listen to the Elevate Construction podcast: (Click here)
-Check out our training programs and certifications: (Click here)
-The Takt Book: (Click here)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction IST. As the company’s owner and principal consultant, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.
On we go