Read 5 min

How to Create an Effective Plan for Your Pre-Construction Meeting

In this blog, we’ll explore the essentials of running a successful pre-construction meeting (also known as a pre-install or preparatory meeting). These meetings are pivotal for aligning trades, ensuring readiness, and setting the tone for a smooth project execution. Here’s how you can make the most out of your pre-construction meetings to empower foremen and create a cohesive team dynamic.

When to Hold the Pre-Construction Meeting:

Schedule your pre-construction meeting three weeks before the work begins. This allows enough time to address unpreparedness and reschedule if necessary, ensuring everyone is aligned well in advance.

Key Areas to Discuss:

  • Overall Project Schedule:
    • Review the schedule in detail, confirming that all foremen and team members understand the timeline.
    • Discuss any final planning items and ensure alignment with the pull plan, look-ahead planning, and weekly work plans.
  • Safety Plan:
    • Clearly outline safety expectations and protocols.
    • Discuss specifics such as tie-offs, shoring for excavations, and other critical safety measures.
  • Quality Standards:
    • Go beyond setting expectations—delve into the methods and processes that ensure quality.
    • Define the key deliverables and benchmarks for maintaining quality throughout the project.
  • Logistics and Coordination:
    • Cover zone maps, trailer layouts, and staging areas for materials and equipment.
    • Discuss how the trades will collaborate and how their work will align with other activities on-site.
  • Risk Management:
    • Review potential risks and opportunities.
    • Use this time to address any red flags or challenges that could impact the project’s progress.
  • Supply Chain and Procurement:
    • Ensure everyone is aware of the procurement log and current status of the supply chain.
    • Align on timelines for materials and equipment delivery.

Creating the Installation Work Package:

Everything discussed in the meeting should be reflected in the installation work package. This package includes:

  • Installation Instructions: Step-by-step guidance for executing the work.
  • Annotated Plans: Updates based on discussions during the meeting.
  • Inspection Criteria: Clear benchmarks for assessing progress and quality.

The meeting minutes should feed directly into these planning deliverables, providing a comprehensive guide for execution and inspection.

If you want to learn more we have:

-Takt Virtual Training: (Click here)
-Check out our Youtube channel for more info: (Click here) 
-Listen to the Elevate Construction podcast: (Click here) 
-Check out our training programs and certifications: (Click here)
-The Takt Book: (Click here)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction IST. As the company’s owner and principal consultant, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.

 

 