Crew Planning: How to Break Work Into Steps So Crews Win Every Day

Crew planning: a foreman reviewing a visual crew board and task lists with crew members in their zone
Read 8 min

I want to talk about the details of crew planning and how to do it in a very effective way, so that every day the crew has what is called full kit. When I got to the outline for this, I fell in love with it. I made the outline, but my brain got a new perspective on it, and I think you are going to love it too. In fact, I am going to turn this outline into a crew planning form and put it into packets.

Short answer: Crew planning gets every crew full kit in its zone within its Takt time. Break the work into zones, start with a single visual of what good looks like, plan backward from the handoff, break out the crew and tasks needed to finish, and give every crew member a templated task list with time markers and buffers for quality checks. Big milestones move managers. Small bite-sized chunks move crews.

What Is the Ultimate Goal of Crew Planning?

The ultimate end of everything in construction, everything that all the project delivery team members do, all of the design, and everything a construction company does, is to get the crew full kit in their zone, in their Takt time. That means they have everything they need to build and finish without stops or restarts:

  • The materials.
  • The tools.
  • The permissions.
  • The layout.
  • The people.
  • The equipment.

That is the ultimate end of everything. If we have been doing the trade partner preparation process properly, all of this should be ready. But we still need to do the best kind of planning at the crew level.

What the Best Foremen Do

As a career general contractor, I have always noticed that the foremen I am most impressed with have detailed lists for their people. I never understood how it all worked together, but now I do. I have finally been able to observe long enough. I have been a worker for a long time, a lead person, and a foreman for a six-month stint, probably not as long as you have been. So I do have experience with this. It is just finally coming together as I get older. Here is the pattern.

Step 1: Break Everything Into Zones

The first thing is the zone size. Depending on your world, it might be the station, the segment in civil, the work package in advanced work packaging, the spool in prefabrication, the segment in your flow diagrams, or the construction work area. Whatever it is, give the crew the right size.

Todd Zabelle says everything should be down to a day. I do not agree. Sometimes Takt times can be one day, two days, three days, or a portion of a day. It is whatever your Takt time is, inside whatever zone size works with it. So the first thing is to break everything out in zones, so we know exactly what we are building in one-piece flow. Plan, build, finish.

Step 2: Start With What Good Looks Like

In the pre-construction meeting, three weeks before the work ever starts, we should have a single visual that shows the ultimate outcome for this installation work package, for the work that goes into the zone inside the Takt time. It should be highly visual, with pictures, something the crew would actually want to use.

I remember somebody being snarky with me about this. They were using Procore, and I said we cannot have it in 35 different locations. They said, it is not in 35 different locations, it is in Procore. Yes, it is in Procore, in 35 different locations. You have to go here, here, here, and here. The plans are over here. The specs are over here. The contract is over here, the inclusions are over here, and the submittals are over here. I want a single page that shows the crew what this is supposed to look like, 100 percent.

Step 3: Don’t Start, Finish

Number three is don’t start, finish. You might be thinking, wait a minute, you have to start if you are going to finish. But work mentally from the end, meaning where the handoff is going to happen to the next contractor, and plan back. What is the handoff going to look like? Everything we do in construction should be from the end forward, planning back.

So start with that framework and ask, what does my scope of work need to look like by the end of my Takt time, before I hand it off?

Let me double down on that. The motto is that we do not end the afternoon foreman huddle until we are ready to build the next day in day-tight compartments, and we do not start anything until we are ready to finish. Don’t start until you are ready to finish. Period. That is the key to construction. Anybody can start. Finish.

Step 4: Break Out the Crew and Tasks to Finish

Once you understand what the finish looks like, break out the crew and the tasks needed to accomplish the finish and the handoff. When you think of it from the end to the front, you have broken it down so you can finish, not just start.

Step 5: Give Every Crew Member a Templated Task List

The next step is even cooler, and it is what I have seen with every great crew. Once you have the steps and all the information, break all the tasks down by crew member, and each crew member gets a list.

That list should be templated. On the first zone, you will make some adjustments. On the second zone, a few more. By the third zone, you should have it pretty locked in.

You can break the list down by person and by the hours of the day, or even minutes within the hour. You are not micromanaging people. You are giving them a guide with time markers for when things should be done. Never rush. Build in plenty of buffers to stop and get quality right. Every worker should leave knowing exactly how they fit, both by task and by time, and exactly where their buffers are to do their quality checks and inspections as part of that list. Never just rush, push, and panic.

Then, inside your crew, you have your visual crew board, with all of this information visible. Everybody has their list, and everybody knows what winning looks like.

What Does Leadership Look Like in Crew Planning?

You also need a great, supportive culture. Leadership is clarity, then training toward that clarity, and then shoulder-to-shoulder support. That is how you make sure your crew is ready to succeed.

If you want to go deeper on this, check out our book, Elevating Construction Crew Leaders.

So here is the challenge. Pick one crew and one zone. Before your next afternoon foreman huddle ends, make sure there is a single visual of what good looks like, plan back from the handoff, and give each crew member a list with time markers and buffers for quality checks.

Bottom line: Big milestones move managers, and small bite-sized chunks move crews.

If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.

Want your team trained on this? See our Last Planner® System and Takt training.

On we go.

FAQ

What is crew planning in construction?

Crew planning is breaking the work into steps so the crew has full kit in its zone within its Takt time. It ends with every crew member holding a task list that shows how they fit by task and by time.

What is full kit for a crew?

Full kit means the crew has the materials, tools, permissions, layout, people, and equipment to build and finish without stops or restarts.

What does “don’t start, finish” mean?

It means planning from the handoff backward. I do not start anything until the crew is ready to finish, because anybody can start.

Should every crew task be broken down to one day?

No. Takt times can be one day, two days, three days, or a portion of a day. The zone size should fit whatever your Takt time is.

How detailed should a crew member’s task list be?

Break it down by person and by hours of the day, or even minutes within the hour, with time markers and buffers for quality checks. It is a guide, not micromanagement.

People Also Read:
What Is a Look Ahead Plan in Construction?
How to Manage a Construction Crew
How Buffers Work in Takt Planning

If you want to learn more we have:

-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.

Share:

    Share Link