Mastering Field Coordination: Using Crew Boards and Work Packages

In this blog, we’ll explore how to use crew boards and installation work packages to improve communication, planning, and work execution for field crews. If you’re a foreman or crew lead looking to enhance how your team operates, these tools will help empower your workers to take charge of quality, logistics, and daily planning. Let’s dive into the Trade Partner Preparation Process, the essentials of Installation Work Packages, and the impact of effective crew boards.

  1. Key Steps in the Trade Partner Preparation Process

To prepare your team and trade partners effectively, there are several critical stages you need to follow:

  • Buyout: Secure the trade partner for the specific scope of work.
  • Contract Execution: Ensure the contract is signed, and the trade partner is compliant.
  • Pre-Mobilization Meeting: Clearly define the deliverables required by the preconstruction meeting.
  • Preconstruction Meeting: Review essential details with foremen and superintendents to set expectations.
  • Work Start & Initial Inspection: Conduct a first-in-place inspection to confirm quality.
  • Ongoing Inspections: Perform regular follow-ups and a final inspection to ensure quality and compliance.

These steps ensure that your crew understands expectations from the outset, reducing the chance of rework and misunderstandings.

  1. How to Create an Effective Installation Work Package (IWP)

An Installation Work Package (IWP) is a vital document that holds all necessary information for the crew to execute their work with clarity and confidence. A well-structured IWP includes:

  • Scope and Activity Details: Clear instructions about what work is to be completed in a specific zone.
  • Cycle Time: Projected duration for each activity, helping the crew manage time effectively.
  • Plans, Specifications, and Layouts: Includes all necessary drawings and any lift layouts required for the task.
  • Job Hazard Analysis (JHA): Covers safety requirements to ensure worker protection.
  • Quality Expectations: Lists standards and checks to guarantee work meets project requirements.

Starting the IWP process early—during buyout, contract review, and pre-mobilization—allows crews to familiarize themselves with all relevant details and requirements. By finalizing the package in the preconstruction meeting, the crew can go to work with everything they need in hand.

  1. Benefits of Using Crew Boards

Crew boards are a powerful tool for visual communication and planning. Here’s how they enhance crew efficiency:

  • Lookahead Plan: This shows the 6-week forecast of tasks, allowing teams to prepare for upcoming work.
  • Weekly Work Plan: Provides weekly goals, handoffs, and commitments to keep everyone on track.
  • Day Planning and Logistics: Allows foremen to sketch the day’s activities, set up material staging, and assign work zones.
  • Daily Agenda and Safety Updates: Ensures the crew is briefed on potential hazards and priorities for the day.

Front Side of the Crew Board: Houses the lookahead plan, weekly work plan, day plan, and logistics. It allows the crew to visualize tasks, plan for safe material handling, and coordinate resources on-site.

Back Side of the Crew Board: Stores work packages that are specific to the crew’s tasks, such as installation instructions, quality checks, and safety protocols. These packets provide easy reference materials that each subgroup or crew member can access on the spot.

  1. Empowering the Crew Through Visual Tools

By using crew boards and IWPs, foremen can address common issues like unclear expectations or repeated discussions of requirements. This system:

  • Encourages Problem-Solving: When crew members have the necessary documents on hand, they’re empowered to identify issues and proactively solve them.
  • Prevents Defective Work: With the right visual tools, crews can stop work to address quality concerns before they progress.
  • Enables Decentralized Command: Crew members have the resources to work independently within the strategic plan, fostering a more efficient workflow.

This method helps create an environment where expectations are clear, quality standards are maintained, and each team member understands their role in achieving the project’s goals.

Conclusion

Using crew boards and IWPs effectively streamlines communication, organizes work processes, and places control into the hands of the crew. This empowers them to work with greater autonomy and confidence, ultimately leading to higher quality and more efficient project completion.

If you’re ready to implement these strategies and elevate your field operations, start by setting up your crew boards and work packages today!

If you want to learn more we have:

-Takt Virtual Training: (Click here)
-Check out our Youtube channel for more info: (Click here) 
-Listen to the Elevate Construction podcast: (Click here) 
-Check out our training programs and certifications: (Click here)
-The Takt Book: (Click here)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction IST. As the company’s owner and principal consultant, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.

 

 

On we go