Is Pre-Construction A Good Investment?

Read 3 min

Is Pre-Construction Planning a Good Investment?

In this blog, we explore one of the most important questions in construction management: Is pre-construction planning worth the investment? The answer is an emphatic, undeniable, trillion-percent YES.

Let’s break down why this phase is so critical, referencing key concepts from the powerful book How Big Things Get Done, along with insights from Elevating Pre-Construction Planning, resources every construction professional should have at their fingertips.

Why Pre-Construction Planning Matters:

You’ve probably heard someone say, “Just throw a superintendent in an office with a set of drawings.” That never works. Pre-construction isn’t about sitting around; it’s about actively shaping the conditions for project success.

In fact, the goal is to complete at least three iterations of the construction plan before breaking ground. Yes, that might sound ambitious, but with the right support (and possibly a pre-con department), it’s possible. And it’s worth it.

By the time you mobilize onsite, you should have:

  • A detailed Takt plan.
  • Zone maps.
  • Logistics plan.
  • A fully designed trailer layout.
  • A clear org chart.
  • A risk and opportunity register.
  • A comprehensive procurement log.
  • And of course, a thoroughly reviewed budget.

Backed by the Numbers:

From the book How Big Things Get Done, we learn from 16,000+ projects worldwide (now likely over 25,000). The statistics are shocking:

  • Only 48% finished on budget.
  • Only 8–9% finished on time.
  • Only 0.5% met owner expectations (budget, schedule, and satisfaction).

Why? Lack of planning.

The Cost of Not Planning:

When projects skip thorough pre-construction, the consequences are steep:

  • Design issues discovered late.
  • Permitting delays.
  • Late procurement of long-lead items like elevators, switchgear, and curtain wall systems.
  • Uncoordinated teams moving in opposite directions.
  • High costs to fix issues during construction.
  • A “Window of Doom” the longer the project takes, the more you’re exposed to black swans (major unforeseen problems).

Solving Problems Where It’s Cheapest:

Here’s the truth: It’s 10x more expensive to solve a problem during construction than it is during pre-con. If you catch it in pre-con, you erase a whiteboard or delete a file. If you catch it in the field, you pause crews, rework installations, lose schedule, and morale drops.

Lean Thinking: Iterate Early

Lean isn’t about iterating in the field while crews wait. It’s about iterating on paper, design, simulate, refine so that when you execute, you’re not wasting time or resources.

Final Thoughts:

Pre-construction planning is the investment that protects every other investment you’ll make in the project. From budget to safety, to team alignment and client satisfaction, it all starts with great planning.

If you want to learn more we have:

-Takt Virtual Training: (Click here)
-Check out our Youtube channel for more info: (Click here) 
-Listen to the Elevate Construction podcast: (Click here) 
-Check out our training programs and certifications: (Click here)
-The Takt Book: (Click here)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction IST. As the company’s owner and principal consultant, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.

 

 

On we go

Posted in All

What Does A Pre-Construction Manager Do?

Read 3 min

What Does a Pre-Construction Manager Actually Do?

In this blog, we’re diving into one of the most crucial roles in the success of any construction project: the Pre-Construction Manager. Whether you’re just learning about this position or looking to improve your current processes, this overview will walk you through the key responsibilities and why this role is absolutely essential.

Why the Pre-Construction Manager Matters:

A pre-construction manager is not just a glorified estimator. They are the conductor of the entire pre-construction orchestra coordinating the design team, trade partners, budget, permitting, scheduling, and more.

Without someone in this role, chaos creeps in. Deadlines get missed. Budgets are blown. Coordination fails. A strong pre-con manager prevents that chaos by keeping everything aligned and flowing.

Key Responsibilities of a Pre-Construction Manager:

  1. Lead Pre-Construction Planning:

From concept to design development, the pre-con manager sets the tone and structure for collaboration. They establish:

  • Communication systems.
  • Meeting cadence.
  • Planning frameworks (Takt, milestones, risk registers).

They ensure the team is aligned early and stays that way.

  1. Manage Budgets & Cost Estimates:

They work closely with estimators to:

  • Track budget in real-time.
  • Compare conceptual, control, and trade estimates.
  • Ensure design aligns with cost expectations (no “design-then-chop” cycles).
  1. Coordinate Design Development:

This includes:

  • System selection for optimal cost and constructability.
  • Feeding build specs to designers.
  • Helping the team design what will be built, not the other way around.
  1. Manage Value Engineering (VE):

Pre-con managers guide VE efforts in real-time:

  • Using A3s to explore problems and solutions.
  • Logging decisions and trade-offs.
  • Ensuring VE supports project goals not just cuts.
  1. Lead Constructability Reviews:

They don’t allow surface-level reviews. Instead, they lead:

  • Deep model checks.
  • Real builder feedback.
  • Constructive coordination between trades and design.
  1. Oversee Planning Deliverables:

They ensure creation and maintenance of:

  • Takt plans.
  • Zone maps.
  • Logistics plans.
  • Procurement logs.
  • Trailer layout and more.
  1. Coordinate Early Trade Partner Input:

Early design assist from trades is a game-changer. The pre-con manager makes it happen by:

  • Securing early LOIs.
  • Looping trades into design (MEP, envelope, elevators).
  • Ensuring design supports buildability and efficiency.
  1. Create Bid Packages & Manage Bidding:

From bid package creation to bid leveling and scope alignment, this role:

  • Helps select the right partners.
  • Ensures clear expectations.
  • Supports strong project launch.
  1. Prepare the Site & Logistics:

They evaluate and coordinate:

  • Existing utility conflicts.
  • Historical preservation needs.
  • Soils and site readiness.
  • Temporary power/water setups.
  1. Unify the Team:

Above all, the pre-construction manager keeps everyone rowing in the same direction, owner, designers, GC, and trades, all focused on shared project outcomes.

Final Thoughts:

A great pre-construction manager is awake at the wheel leading with clarity, intention, and care. If you want your project to hit its targets, start strong, and avoid chaos, this role is non-negotiable.

If you want to learn more we have:

-Takt Virtual Training: (Click here)
-Check out our Youtube channel for more info: (Click here) 
-Listen to the Elevate Construction podcast: (Click here) 
-Check out our training programs and certifications: (Click here)
-The Takt Book: (Click here)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction IST. As the company’s owner and principal consultant, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.

 

 

On we go

Posted in All

Who Should Ideally Be At The Pre-Construction Conference?

Read 4 min

Who Should Be at Your Pre-Construction Conference?

Who should ideally be at the pre-construction conference on a construction project? In this blog, I’ll walk you through exactly who should attend and why, plus a bit about what this meeting is and why it matters.

Let’s dive in.

What Is the Pre-Construction Conference?

I often talk about pre-construction in three different ways:

  1. Pre-Construction: Everything from concept design to CDs, to signing a prime agreement, and getting an NTP (Notice to Proceed). This is all the upfront work that supports the designers and ensures the project starts on solid ground.
  2. Pre-Construction Conference: This is the focus of this blog. It happens before the overall job kicks off usually 5 to 60 days prior, depending on the project. It might involve the owner or an inspector and sets the tone for how the job will be run.
  3. Pre-Construction Meetings: Also called pre-install or preparatory meetings, these occur about three weeks before a trade starts work on-site.

This blog is about the pre-construction conference, which aligns the whole team before boots hit the ground.

Why the Pre-Construction Conference Matters:

This meeting ensures the contractor and trade partners are fully oriented to how the project will be managed. Key topics include:

  • Project management systems.
  • Inspections.
  • Site logistics.
  • Neighbor relations.
  • Quality expectations.

How you start is how the job will go. So, let’s get the right people in the room.

Who Should Be There?

  1. Owner or Client Representative:

They set expectations for project management systems and share their top 10 priorities whether it’s staying off the news, waterproofing concerns, or anything else critical. Their voice must be heard from day one.

  1. General Contractor: Project Manager & Superintendent:

As Derek Kirkland says: “The PM reads the owner’s mind. The Superintendent sees the future.” These roles must show up to listen, align, and deliver.

  1. Field & Project Engineers:

The PE will need to understand RFI and submittal processes, pay application flows, survey requirements, and quality control. Their early involvement drives execution and buy-in.

  1. Architects & Engineers (Design Team):

The design team must explain submittal expectations, turnaround times, and clarify design responsibilities. Their presence ensures alignment with owner vision and code requirements.

  1. Key Trade Partners:

Electrical, mechanical, plumbing, concrete, framing, any of the driving trades. Why? They likely have experience with the owner or inspector and can add credibility and clarity. Don’t let important messages get lost in translation.

  1. Corporate Support (Optional but Helpful):

Scheduling managers, quality or safety support staff, if they will play a key role, they should attend. It’s better to over-communicate early.

  1. Other Stakeholders:
  • Project Inspector (especially the lead inspector).
  • Adjacent or future Facilities Managers.
  • Anyone else with a stake in project execution and alignment.

Final Thoughts

If you’re going to run a project right, you need a pre-construction conference that aligns everyone. This meeting is your chance to get on the same page and make sure there is a page to get on.

If you want to learn more we have:

-Takt Virtual Training: (Click here)
-Check out our Youtube channel for more info: (Click here) 
-Listen to the Elevate Construction podcast: (Click here) 
-Check out our training programs and certifications: (Click here)
-The Takt Book: (Click here)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction IST. As the company’s owner and principal consultant, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.

 

On we go

 

Posted in All