What a Superintendent Should Actually Do During Pre-Construction
Here’s the deal. Too many superintendents get brought into pre-construction and then simply parked at an empty desk with a set of drawings and a vague instruction to get familiar with the project. That is not useful, it does not fit how a genuinely field focused person actually works best, and it wastes one of the highest leverage windows available on the entire project.
Why This Time Deserves Real Extra Effort
I am generally not an advocate for working weekends or constant overtime. Pre-construction is the one genuine exception worth making. If there is ever a moment to put in extra hours and real additional effort, it is here, before the job actually starts, specifically so the field phase itself runs smoothly and you can genuinely go home on time once real construction begins.
An hour spent in pre-construction is worth a week spent recovering from a problem in the field. A day spent here is worth a month later. That ratio alone should settle any debate about where the real effort genuinely belongs.
Think about what that ratio actually means in practice. A superintendent who spends an extra evening working through a logistics plan or a zone map during pre-construction is effectively buying back an entire week of chaos later, the kind that shows up as rework, miscommunication, and crews standing around waiting on something that should have already been resolved.
What Actually Belongs in This Time, Step by Step
None of this means sitting bored behind a desk staring at drawings. There is a specific, structured sequence worth following instead.
Start by building the macro level Takt plan, including a real logistics plan and genuine zone maps. Begin long lead procurement immediately. Start actively supporting your designers rather than waiting passively for finished documents. Run real time constructability reviews and genuine budget analysis as the design develops, rather than after it is locked. Look closely at the land itself and the utilities serving it, identifying any make ready work, like shoring, that will genuinely be required before work can actually begin.
Here are the specific planning deliverables that should come out of this detailed phase.
- A real plan and schedule, built alongside genuine zone maps and logistics maps rather than treated as separate afterthoughts.
- A deliberately designed project trailer and a clear plan for how the project team itself will actually be organized and broken out.
- A genuine risk and opportunity register, tracking long lead procurement and supply chain items specifically.
From there, review the site make ready requirements directly, read the actual soils report rather than skimming a summary, and map out the first ninety days in detail, both the ninety days leading up to notice to proceed and the ninety days immediately following it.
The Question Worth Asking Constantly Throughout
Keep returning to one genuinely useful question throughout this entire process. What could stop construction in six months. That question alone tends to surface real risks long before they would otherwise become visible, giving you genuine time to actually address them.
A practical extension of that question is researching every authority having jurisdiction requirement that could genuinely hold up the project later. Do you need two paved roads and active fire hydrants in place before you can go vertical. Do you need a vertical standpipe installed for the fire sprinkler system before building above the third floor. These specific requirements vary significantly by jurisdiction, and AI tools can genuinely help you research them thoroughly and quickly, well ahead of when they would otherwise surface as a real problem.
Watch for these specific categories of jurisdiction requirements worth researching proactively during pre-construction rather than discovering them later.
- Infrastructure requirements, like paved roads or active fire hydrants, that must exist before certain construction activities can legally proceed.
- Fire and life safety system requirements, like standpipes, that must be installed before building beyond a specific height or floor count.
- Any other authority having jurisdiction requirement specific to your exact location and project type that could otherwise halt work unexpectedly.
There is genuinely no such thing as too much research during this phase. Every hour spent here protects real time later. The teams that treat jurisdiction research as a box to check quickly, rather than genuine investigation worth real time, are consistently the ones who discover a serious constraint only once it has already cost them weeks on the schedule.
Why I Increased My Own Recommendation on Fresh Eyes Meetings
I used to recommend one to three fresh eyes meetings before a project starts, where an outside perspective tears the plan apart specifically to find every flaw worth catching early. I have since increased that recommendation significantly. On our own next project, I told our team directly that I want eight separate fresh eyes meetings, continually tearing the plan apart until it is genuinely right before we ever break ground.
That increase was not arbitrary. Each additional round tends to surface issues the previous ones missed, and the cost of catching a problem during one more meeting is genuinely nothing compared to the cost of discovering it once real construction is already underway.
I understand the instinct to treat eight meetings as excessive before you have actually tried it. In practice, the eighth meeting rarely feels redundant. It tends to catch something the first seven genuinely missed, which is exactly why the number keeps climbing rather than settling back down once teams actually experience the difference.
Why You Do Not Have to Do This Entirely Alone
If you are working through this process on your own, a resource like Elevating Pre-Construction Planning walks through this exact sequence visually, step by step, and the First Planner System audiobook covers the same material for anyone who learns better by listening during a commute. If you would rather bring in real support, a dedicated planning team can work alongside you directly, whether that means staffing a single position or bringing in a full team to handle the work with you and genuinely reduce risk across the entire project.
Building This Structure Into Your Own Pre-Construction Process
None of this requires guessing at what to do with your time during pre-construction. It requires following this same sequence deliberately, protecting genuine time for it, and treating it with the seriousness its real leverage actually deserves.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your superintendents build exactly this kind of structured pre-construction process, rather than being handed a set of drawings and left to figure out where to start on their own.
So here is the challenge. Before your next project reaches pre-construction, map out which of these specific steps your current process already covers well, and which ones tend to get skipped or rushed. Whichever step consistently gets the least attention is exactly where your next field level problem is most likely already forming.
Jason Schroeder said it plainly: “An hour in precon is worth a week in the field. A day in precon is worth a month in the field.” Protect that time deliberately, and the field phase genuinely becomes easier because of it.
On we go.
FAQ
Why does the article recommend extra effort specifically during pre-construction rather than throughout the entire project?
Because problems caught and solved during pre-construction are dramatically cheaper and easier to fix than the same problems discovered once real construction is already underway. The article frames this as an extremely high leverage trade, where an hour invested early saves far more time later, which is why it treats this specific phase as the exception to generally avoiding overtime.
What is the actual purpose of mapping out the first ninety days before and after notice to proceed?
Because the early weeks of a project are where momentum either builds correctly or starts falling behind immediately, and detailed planning for that specific window helps ensure the project starts strong rather than scrambling to catch up from the very beginning. Covering both the ninety days before and after notice to proceed ensures preparation work and early execution are planned together rather than treated as separate phases.
Why does the article recommend researching authority having jurisdiction requirements so far in advance?
Because requirements like needing paved roads, active fire hydrants, or specific fire safety systems in place before certain construction activities can proceed vary significantly by location and can genuinely halt work if discovered too late. Researching these requirements thoroughly during pre-construction gives a team real time to plan around them, rather than discovering a hard stop once construction is already underway.
Why did the recommended number of fresh eyes meetings increase so significantly, from one to three up to eight?
Because each additional round of genuine outside review tends to surface issues the previous rounds missed, and the cost of running one more meeting is minimal compared to the cost of a problem discovered once construction has already started. The increase reflects a growing recognition that more thorough review during pre-construction consistently pays for itself many times over.
If you want to learn more we have:
-Takt Virtual Training: (Click here)
-Check out our Youtube channel for more info: (Click here)
-Listen to the Elevate Construction podcast: (Click here)
-Check out our training programs and certifications: (Click here)
-The Takt Book: (Click here)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction IST. As the company’s owner and principal consultant, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.