There is so much in this concept of going the same speed. Our trades should be moving through the project at the same speed. Let me say that one more time: our trades should move through the project at the same speed. That is how you flow in manufacturing, in pods, and in construction. Pull will get you part of the way there, but flow is when it really happens. In this post, I want to bring out a concept I have never talked about before: unnecessary pushing.
Short answer: Unnecessary pushing is driving a trade to go faster than the pace of the system. Your project will never go faster than its slowest trade, zone, or bottleneck, so pushing people hard between bottlenecks only creates more stops and restarts, and it hurts people. Instead, level the system: expand bottlenecks, fix problems, remove roadblocks, and keep every trade at the same speed, the same distance apart.
What Is Unnecessary Pushing in Construction?
If you want to flow, your trades go through the project at the same speed and the same distance apart. That is the heart of the Takt Production System. Unnecessary pushing is what happens when we ignore it. We push people hard between the roadblocks, between the bottlenecks, between the slowest trades, and between the slowest Takt zones. When we do that, we are hurting people, burdening people, fatiguing people, and overwhelming people for no gain.
This is one of the big reasons I am against the forward-and-backward-pass CPM push that everybody is in. It is an unnecessary push. I go deeper on the difference in Flow, Pull, & Push.
The Freeway Analogy
Let’s imagine a freeway. I love what Hal Macomber taught me about picturing a freeway with on-ramps and off-ramps. On the ramps, there is high variation. In the fast lane, there is high utilization. Both can slow you down.
When I was at Hensel Phelps, they had us take a four-hour driving course with a professional driving instructor. He was always telling us to scan farther ahead. Don’t just look 100 feet in front of you. Scan the signs and the cars, and anticipate what people are trying to do. He would always have us default to the middle lane, where there was flow. I love that analogy.
So when do you have problems on a freeway? It is always when something happens and you can’t go the same speed, the same distance apart:
- You bump up on somebody and end up tailgating them.
- You come onto the on-ramp or head to the off-ramp, and you haven’t planned far enough ahead to fit in between cars at the right speed.
- You are in the fast lane, where cars keep moving around and there is so much variation.
As soon as there is an interruption, there is a ripple, then a bottleneck, then a traffic jam.
Why Speeding Up Between Traffic Jams Gains Nothing
Here is what is interesting. Between one traffic jam and the next, cars speed up once they get out of the first jam, just to hit the next one. They get past one stoplight just to speed up and hit another stoplight. They gain nothing by going faster than they need to go.
You will never go faster than the slowest car. You will never go faster than the slowest traffic jam. And in construction, you will never go faster than the slowest trade.
It is actually the act of going fast and then stopping hard that perpetuates the interruption. If cars went a little slower in between, the traffic jam would open up a little, they would ease into it, and traffic speeds would level out.
What Does Unnecessary Pushing Look Like on a Jobsite?
You have seen it on a project. “This is our slow trade, and we have a lot of people right on the date, but let’s push the electrician or the framer to go fast and get out ahead three or four zones.” Why? Your whole system is only going to go as fast as the slowest constraint, the slowest bottleneck, the slowest trade, or the slowest zone. The pace setters set the speed of the train.
When one contractor tries to get way ahead, or the superintendent pushes them too far ahead, they just stop again. You had one stop already. Now you have two stops to deal with. If you keep pushing people to go fast when there is no need, faster than the pace of the system, you are creating more stops and starts, more restarts, more bottlenecks, and more constraints.
| Unnecessary pushing | Leveling the system |
|---|---|
| Push one trade three or four zones ahead | Keep every trade at the same speed, the same distance apart |
| Two stops to deal with instead of one | One problem to deal with, and the capacity to fix it |
| Fatigued, overburdened crews | Steady, even work |
| Attention on driving fast between bottlenecks | Attention on creating capacity |
How Do You Stop Pushing and Level the Flow?
Instead of pushing and hurting people, level the system:
- Expand your bottlenecks. The constraint sets the pace, so that is where your help goes.
- Fix problems.
- Remove roadblocks.
- Turn your attention away from pushing people and driving fast between the traffic jams, and toward creating capacity and leveling the work.
Have the trades go in an even flow, help each other out, regulate the system, and level the work. Then you still only have that one problem to deal with, and you can use your capacity, resources, and focus to fix it. Speed comes from stability, not from pushing.
Could Faster Trades Help the Slower Ones?
One of these days, we have to get to a point where, if one trade is able to be way ahead, they can take over certain aspects of the work by contract to help the slower ones. Can they help swarm? Can they use some of their capacity for the other trades? It would ultimately benefit them.
Here is what I mean. If I were that contractor, way ahead and jamming out doing my thing, and I saw the trades around me going slow, I would make more money spending a little time helping the others, leveling the overall system, and removing the bottlenecks than I would staying in my area and starting and stopping all the time. I am not saying go do it tomorrow. Contractually, we have to get to a point where we can work these situations out. But stop pushing people past the pace of the system.
If you want to go deeper on flowing on a rhythm instead of pushing, our book Flowing Together on a Takt Time Pull walks through it.
So here is the challenge. On your next field walk, find the trade that is racing ahead of the train and the trade that is setting the pace. Stop pushing the first one, and put your capacity, resources, and focus into the second.
Bottom line: You will never go faster than your slowest trade, so stop pushing people and level the system instead.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
Want your team trained on this? See our Last Planner® System and Takt training.
On we go.
FAQ
What is unnecessary pushing in construction?
It is pushing a trade to go faster than the pace of the whole system. It adds stops and restarts without making the project finish any sooner, and it hurts people.
Why can’t a project go faster than its slowest trade?
Every trade in the train depends on the zones around it. Like a car racing between traffic jams, a trade that races ahead just stops again at the next bottleneck.
What should a superintendent do instead of pushing?
Level the system. Expand your bottlenecks, fix problems, remove roadblocks, and keep every trade at the same speed, the same distance apart.
How is unnecessary pushing like a traffic jam?
Cars that speed up between jams gain nothing, and the hard stops keep the jam going. If they slow down a little and ease in, traffic levels out, and trades work the same way.
People Also Read:
Speed Comes From Stability
Flow, Pull, & Push
Drum-Buffer-Rope Analogy: The Constraint Sets the Pace
The Engines of the Train: Pace Setters in Construction Flow
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.