Going Paperless Should Not Be the Goal on Construction Projects

Project trailer wall with printed zone maps next to a screen showing the takt plan
Read 7 min

I’m deviating a little from the takt and Last Planner implementation series for a topic that has to be addressed: going paperless. Back at Hensel Phelps in the Western District, a Bluebeam rep was showing us all the cool things we could do, and the biggest rage was, we’re going paperless. It almost seemed like the more we went paperless, the more paper we printed. But I was proud to see software like Bluebeam letting us do so much online.

Short answer: Going paperless should not be the primary goal on a project. The primary goal is to communicate properly and optimize the whole. Use thoroughly tested technology and screens, but keep key visuals in the trailer, let trade partners print zone control maps and plans, and print your wayfinding signage, because rework costs far more than paper.

What Did Paperless Look Like When It Worked?

On a design-build cancer center project, I was in charge of the 3D coordination and BIM effort, the project execution plan, and the team, working with Jared Davis. It was a fantastic experience. We went as paperless as we possibly could: iPads for the foremen, BIM 360 Field for our quality checklists, and drawings on the iPads. I love it. I think it’s great.

But I want to offer a different perspective. Paperless should not be our primary goal. Our primary goal should be to communicate properly and to optimize the whole. If we can do that as paperless as possible, that’s great.

What Happened on the Project That Wanted Zero Paper?

This ties into our Last Planner implementation. I was going down the implementation checklist with one of our process improvement engineers. Past step five, the next steps were:

  • Create your weekly work plan
  • Set up your trade partner weekly tactical meetings
  • Create your meeting agendas
  • Get your visuals on the wall and set up your trailer
  • Begin your meeting cycle
  • Make sure your worker huddles are set up
  • Start implementing takt zone control and takt steering
  • Get all the trades in their wagons as quickly as possible
  • Begin reporting and help the client manage delays

The team gave me kind of a sad face. They said the client was really fighting us on project visuals, because they don’t want anything printed on the wall. They want to go 100% paperless. I was freaking out. How are you going to run these meetings? So we pivoted to having the takt plan, zone maps, and everything on screens, and I’m fine with that. I love using Bluebeam for it. I’ve done it before, and I’ll do it again.

Is the Rework Worth a Few Sheets of Paper?

But when we’re hindered from communicating properly by that overriding goal, here’s what I’m afraid of. I don’t know this for a fact. If we reduce a little paper to save trees, how much communication breaks down? How much variation does that create in the field? How many materials, dollars, hours, and other resources does it cost?

Cost of skipping the paper Ask yourself
Rework Is the rework worth a couple of sheets of paper?
Wasted time Is the waste of time worth it?
Wrong materials If materials weren’t installed or ordered properly and must be reordered, is the gas, fuel, shipping, time, new materials, chemicals, disposal, and waste worth the paper on the quality checklist that could have prevented it?
Plywood What’s a couple of pieces of paper versus a bunk of plywood to re-form something?

Let’s not pole-vault over small things and cause a bigger problem than is actually there. Remember Donella Meadows’ rule from Thinking in Systems: “Thou shalt not distort, delay, or withhold information.” That negatively affects complex systems, because you lose your feedback loop.

If you put a chokehold on everybody about being paperless, and now your foremen don’t have the right communication, you don’t have the right conference room setup, the right visuals, or the right wayfinding signage on site, that would be a darn shame. You’re prioritizing a tenth of a tree over human beings, people’s lives, and things that really matter. I think we can do both.

How Do You Do Both?

  1. Get everything into the best systems, following Toyota’s rule to “use only reliable, thoroughly tested technology that serves your people and processes,” not just all technology.
  2. Buy your screens, software, and computers, and get as many systems online as you need. You might check the materials and waste screens cause versus paper, so you’re not myopic.
  3. Design your conference room and trailer to have at least your zone map visuals, logistics plan, and key items on the board for visual, open collaboration with your trade partners.
  4. Don’t restrict trade partners from printing zone control maps in the field. If they have iPads, great. Tablets can reach them through a QR code, which we make for our clients at Elevate and LeanTakt. But if a trade partner needs a printed set of plans or a printed zone control map, don’t restrict them. By creating flow, they’ll save so many other resources that it’s worth the paper.
  5. Don’t skimp on wayfinding signage. Print those signs and make sure they’re put in right.

See Visual Area Boards and Signage Like Airports.

What Should the Number One Goal Be?

Going paperless should not be the primary goal. It can be a secondary or ancillary goal. The number one goal should be to create flow, optimize the project and the whole, care for our people, communicate, and make sure everybody is working as a healthy, stable team. If we can do that while going paperless, great. But don’t ever let going paperless restrict you from doing the right thing. Read Zone Control: How to Manage the Speed of the Train.

So here is the challenge. Walk your trailer and your site this week. If any zone map, logistics plan, or wayfinding sign is missing because of a paperless rule, put it back up.

Bottom line: Communicate properly and optimize the whole first. Paperless is a bonus, not the goal.

If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.

On we go.

Frequently Asked Questions

Should a construction project go 100% paperless?

Paperless can be a secondary or ancillary goal, but not the primary one. The number one goal is to create flow, optimize the whole, care for people, and communicate. If you can do that paperless, great, but don’t let it stop you from doing the right thing.

What should still be printed on a lean project?

Zone map visuals, the logistics plan, and key items in the conference room for open collaboration; printed zone control maps and plans for trade partners who need them; and wayfinding signage on site.

What is Donella Meadows’ rule about information in systems?

Thou shalt not distort, delay, or withhold information. Bad or late information breaks the feedback loop that a complex system needs to correct itself.

People Also Read:
Lean Onboarding Series – Visual Management Systems
Visual Planning in Construction
Technology in Pre-construction
5S and Mieruka: How Cleanliness and Visuals Build Culture

If you want to learn more we have:

-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.