We’re almost there. This is the third-to-last step in the Last Planner implementation series: get all trades into their wagons as quickly as possible. I’ll also fold in the next step, begin reporting on progress.
Short answer: Once zone control and the six steering strategies are in place, get every trade into its wagon on takt time at the same speed. Don’t let fast trades race ahead. Use that capacity to help your slowest trades, because the project only goes as fast as its bottlenecks. Report progress daily or weekly and point resources, crews, zone managers, and even RFIs at the slowest areas first.
What Makes the Steering Strategies Click?
One thing I should have said in the last post: the takt steering and control strategies really click when we do the takt simulation with groups. We have fantastic trainers throughout our organization who can come run those simulations. If you have zones and takt time but you’re not implementing zone control, the simulation is going to get it there for you. See Our New Lean Simulation Kit.
What Happened When Trades Started to Jam?
Let me tell you a story. I won’t say what company or who it is, but it’s a great superintendent at a great company, and they were getting in trouble schedule-wise. A huge project. The owner was concerned, and they were great people too. They just needed help getting back on track. We implemented the takt production system and started working with them. That’s the group that renamed superintendents as zone managers, which I really liked.
As they started using the takt production system, there were areas where they could now go faster, so they did. Some roadblocks were being removed and some trades were going faster, but other areas were still behind. It wasn’t one consistent train at that point. It was almost multiple trains. And they said, this is the takt production system, we’re able to go faster, so they started to jam.
If you looked at the data date, as they call it in P6, the current date on the takt plan, you’d see a reverse S: trades going fast on top and slowing down when they hit the roadblocks. The tendency was, we can go faster, let’s go faster everywhere we can. And I said, no, no, no. Go the same speed consistently.
Why Shouldn’t Fast Trades Go Faster?
Even if certain areas can go faster, don’t. I know it sounds funny. Use your time, resources, and acceleration to remove roadblocks and get the behind-schedule folks caught up. Can labor be transferred? Can help be given? Can zone managers spend more time in those other zones and let the crews doing well do their thing? Don’t ignore them, but put the focus on getting your slowest trades, slowest wagons, and slowest parts of the train going the right speed.
I was panicking at that backward S. I want all current production in a straight line with the current date, because that’s the only way you create flow. Faster trades look good on paper, but the whole project only goes as fast as your slowest trades, so it doesn’t help your overall schedule. Read How to Help Your Bottlenecks.
How Did They Get Back in Line?
Every week I said, get back in line, get back in line. Get the trades in their wagons and in their zones where they’re supposed to be, as fast as we can. They were great people. It just took a couple of weeks to get on the same page. Then they started getting everyone in line. The S shortened to a squiggle, then got more vertical, and that’s when they started gaining time, because you only go as fast as your slowest trades.
| What you see on the takt plan | What it means |
|---|---|
| Reverse S against the current date | Multiple trains at different speeds, with fast trades racing and others stuck at roadblocks |
| A squiggle | Trades getting back in line |
| A straight vertical line | One train at one speed, creating flow and gaining time |
Is It a Free-for-All?
Pull plans are great. Last Planner is great. But you have to be able to see your bottlenecks. So finalize your formats, implement zone control, watch for the key things, implement the six takt steering strategies, and then get all the trades into their wagons on their takt time. It’s not a free-for-all. It’s getting them all going the same speed. If they’re not going the same speed, they’re different trains. If they are, they’re one train, and that single train is what creates flow.
How Do You Report on Progress?
Once you’re watching this daily or weekly, report on progress, and do anything you can as a project team to not just clear roadblocks but also reallocate resources and keep the focus on your bottlenecks, because you won’t go any faster than them. In your afternoon foreman huddles, ask:
- Can resources come over here?
- Can crews from faster areas come over here?
- Can we focus our efforts over here?
- Can zone control managers be over here?
- What can the other trades learn from the trades doing well?
Point the team to the fact that it doesn’t matter how fast they’re going or how well they’re doing individually. We need to optimize the whole. Communicate it to the workers, zone control managers, foremen, and project team. Even if an office person is working on RFIs for the fast area and the slow area, prioritize the slow area. See Lean Onboarding Series – Bottlenecks.
Top Performers or Slowest Trades?
It’s the opposite of how we deal with people in organizational structures. There, I always say work with your top performers. In the field with the trades, always work with your slowest trades and the ones you’re struggling with most. Don’t forget the high performers. As Matthew 23:23 says, this ye ought to have done, and not to leave the other undone. Keep them going, but speed up your slowest trades.
So here is the challenge. Look at your takt plan against today’s date. If you see an S, pick your slowest trade and move one resource, one crew, or one zone manager’s time to it this week.
Bottom line: No going slower, no going faster. One train, one speed, and the genius of the team focused on the slowest wagons.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
On we go.
Takt and Last Planner Implementation series:
Previous: Six Takt Steering Strategies
Next: Help Clients Manage Delays
Frequently Asked Questions
What does get all trades into their wagons mean in takt?
Get every trade into its assigned zone on its takt time, at the same speed, as quickly as possible. If trades go different speeds, they’re different trains. If they all go the same speed, they’re one train, and that single train creates flow.
Should fast trades go faster in a takt plan?
No. Even if certain areas can go faster, don’t. Use that time, those resources, and that acceleration to remove roadblocks and get the behind-schedule trades caught up, because the whole project only goes as fast as your slowest trades.
What is the reverse S on a takt plan?
When some trades race ahead and others slow down at roadblocks, current production plotted against the current date forms a backward S. The goal is a straight vertical line with the current date, with no going slower and no going faster.
People Also Read:
What Are My Bottlenecks?
Theory of Constraints Explained
Auto-Regulating Bottlenecks
Zone Control: How to Manage the Speed of the Train
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.