This post continues the How Big Things Get Done series with how to iterate. The last post covered the pushing fallacies. When I presented this material, I closed with the tenth man, or tenth woman, rule: someone who challenges the pushing fallacies and the fallacy of wishful thinking. Wishful thinking is not a strategy. The optimists in your organization can be your most dangerous people in preconstruction, because you cannot assume things will go well. Things will go wrong, and we have to see them and deal with them. Data is your friend. Felipe Engineer recently shared a quote from Dr. Deming: without data, you’re just another person with an opinion.
Short answer: Think right to left, starting from the goal and working back to the start date. Then iterate fast on paper in preconstruction, not during construction. Build a maximum virtual product before you break ground.
What Does Thinking Right to Left Mean?
Authors Bent Flyvbjerg and Dan Gardner suggest thinking right to left:
- What’s your goal?
- When should you start the project?
- What are the steps to take together?
- Who should be on the team?
I always start from the right. What is the takt plan on a macro level, start to finish, with all of your phases interconnected, forming an overall project plan? People think, I’m in precon, let’s start with the drawings. No. Start with the concept in conceptual or schematic design, create a macro-level takt plan, and stay with the design as you build out that structure.
That structure will tell you everything. It will inform design and the phases of design. It will tell you whether the plan is vetted. It will tell you how much time you need for long-lead procurement, design, contracting, coordination, procurement, and permitting. And it will tell you when you’re ready to begin. Start with substantial completion and work the structure back to when you should start. Read Winning in Preconstruction!.
What Are the Preconstruction Steps?
| Phase | Steps |
|---|---|
| Schematic design | Organize the precon team. Know the overall duration. Check general conditions and requirements. Update the initial budget and macro-level takt plan. Do utility and geotech reviews, start BIM coordination, plan material buyout, start permits, and develop team positions. |
| Design development | Run the buyout log, bring in design-assist partners, involve builders, do a constructability review, refine the takt plan, finalize major milestones, and do risk and budget reviews. |
| Construction documents | Finalize the takt plan, zone maps, logistics plan, roadblock tracker, risk and opportunity register, and procurement log. Update safety and quality plans, create a 90-day mobilization schedule, build the team, and set up the trailer. |
| Final | Hold a fresh eyes meeting, finalize costs, establish the GMP, and sign the prime agreement. |
Only when that’s done can you answer, when should we start? It’s not left to right. It’s right to left.
Why Iterate in Planning Instead of in the Field?
What’s the worst thing that can happen during planning? The whiteboard is erased. Oops. What’s the worst that can happen during delivery? Collapses, deaths, overruns, ruined careers, failed projects, hurt people, and overburdened trade partners. We must limit our exposure to disaster.
I’ve been lectured by lean consultants who say they don’t do much predictive planning, that they rely on pull plans, six-week lookahead plans, and weekly work plans, and that you shouldn’t plan that far ahead. Learning lean and then having a fixed mindset about it and never iterating makes no sense. I made a comment recently that some found offensive, but I’m sticking with it: why aren’t we at Last Planner 7.0? Why are we still using the same thing? Is a lean system really lean if we’re still on the first version? When we wrote the textbook, there was a second version, then a third, and next year there will be a fourth. The training and the data advance every time. Lean means we iterate.
Projects don’t go bad. They start bad, because we didn’t have a plan. If I had a nickel for every lean consultant who told me not to plan in enough detail in preconstruction, I’d probably have 50 bucks. Saying not to do an early plan in preconstruction hurts people. Is what I’m saying a departure from lean? No. Read In Defense of Last Planner.
What Is a Maximum Virtual Product?
We want a maximum virtual product, not a minimum viable product, on planning. Lean thinking says plan and iterate fast. But make sure the fast iteration happens in the planning stage, not during construction. I don’t care about collaborating with trades at the last minute without a target plan when we don’t have the materials. I care about making a target plan in precon with the trades, so we queue up the supply chains. Then in construction we can make refinements with the trades, still have the materials, and still execute on time. Iterating early on paper will uncover problems, so whatever can be done in planning should be done as thoroughly as possible.
How Does Pixar Iterate?
Going right into it and winging it is what Disney did with the movie Home on the Range. What I’m describing, and what the book describes, is what Pixar does. They take several months to develop a storyline of about 12 pages. A rough draft is written, there’s a feedback round with an audience, then another draft and another feedback session. Then the movie is made in rough form, Pixar employees watch it, and the director meets with a brain trust to receive substantial criticism. Rewrites are completed and it’s refilmed, generally eight times. Then the real animation begins, voice actors record, and the score and sound effects are added. What audiences see is generally the ninth iteration.
Sydney Opera House vs. the Guggenheim
For the Sydney Opera House, optimistic planning was based on assumptions, and the final design wasn’t finished until many months into construction. When the original design proved impossible, completed work had to be demolished and restarted. The architect left Australia in disgrace and never saw the finished building. A five-year plan stretched to 14 years, at 1,400% over the estimated cost.
For the Guggenheim, Frank Gehry built with blocks and models, multiple models each day at various scales. After two weeks of models, he had his final exterior design. He spent two years creating thousands of iterations in 3D modeling software. The project was delivered on time at 3% less than expected. That’s experience meeting experimentation. Gehry said they use all available technology to quantify the building’s elements precisely, so there’s not a lot of guessing. In his practice, they don’t let the client start construction until they are sure the building is within budget and meets requirements. His 76-story 8 Spruce Street tower in New York City had no change orders.
Have I Seen This Work?
I’ve experienced it. On a pharmacy project for the University of Arizona in Tucson, a complex renovation where we were building over another building, the designer kept iterating. We didn’t start or finalize the GMP until we had clash-detected the major clashes in the design models, finished the drawings, done multiple constructability reviews, and gotten the drawings accurate. We had a well-vetted plan and team. That project finished on time, on budget, with raving fans. It can be done. Architects deliver what the customer asks for. It’s time for owners to do this right.
So here is the challenge. On your next precon, start right to left from substantial completion, and run at least one more iteration of the plan on paper than you think you need.
Bottom line: Think slow and act fast. Do the iterations, take the time, and deliver a quality product.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
Want your team trained on this? See our Last Planner® System and Takt training.
On we go.
How Big Things Get Done series:
Previous: The Pushing Fallacies
Next: Experience
Frequently Asked Questions
What does thinking right to left mean in project planning?
Start with the goal: a macro-level takt plan from start to finish with substantial completion. Work the structure back to when you should start, then decide the steps and who should be on the team.
What is a maximum virtual product?
Building the project thoroughly on paper before breaking ground. Iterate fast in the planning stage, not during construction, so problems are uncovered while the worst outcome is an erased whiteboard.
What did the Sydney Opera House and the Guggenheim teach about iteration?
The Sydney Opera House started on optimistic assumptions and ran from five years to 14 at 1,400% over cost. Frank Gehry iterated with models and 3D software, and the Guggenheim was delivered on time and 3% under budget.
People Also Read:
Last Planner System Explained
Pre-Construction Planning: The Five Must-Do Items
Hurry Up and Plan
Get Rid of the Word Should in Pre-Construction Planning
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.