Fresh Eyes Review: What I Look for on a Construction Field Walk

Fresh eyes review: a construction team walking through a production plan and zone maps on a conference room wall
Read 9 min

Here’s the deal. A fresh eyes review is not an inspection. The purpose of the field walk is to get a second set of eyes to support the experts, the on-site team, with the system components. If we do it properly, people leave feeling like the A+ people got support to make the system even more A+. I recently did one with a project team that is doing remarkable work, and I want to share how it went.

Short answer: A fresh eyes review is a field walk where a second set of eyes supports the experts on site, not a critique of the people. Start by asking the team for their biggest system problems. Then dig in with questions: procurement logs, delivery scheduling, meeting attendance, and zone control. Offer ideas, like a two-gate system, weekly contractor grading, and a daily correction system, and then let the team decide what will actually work.

Start With the Team’s Biggest System Problems

I always start by asking permission and listening. What are the biggest problems you are dealing with, from a system or external factor standpoint? And I say it often: this is a system thing, not a person thing.

The team told me that starting Takt scheduling in the middle of the project was tough, and so was getting MEP prime contractors bought in on a multi-prime job. When I asked what the biggest problem was right now, they named three:

  1. Material procurement.
  2. Site logistics and access.
  3. Meeting attendance by the trades.
Problem What I asked Idea for the team
Procurement Are active items in the procurement log? Do the PM and superintendent meet weekly on it? A weekly procurement check with a project engineer stand and deliver
Deliveries and access What are the top three annoyances? A two-gate system and seven minutes on deliveries in the afternoon foreman huddle
Meeting attendance Are expectations clear, and are the meetings adding value? Weekly contractor grading on a few non-subjective items

What Is Lead Time, Really?

We started with procurement. One trade partner had been lagging behind and had not been fully open about why, and the problem only showed up two weeks late. The active items were not in the procurement log, and the PM and superintendent were not meeting weekly on it.

One quick point on terms. Lead time is not just fabrication. Technically, it is the total time from start to delivery:

  1. Hire the contractor and execute the contract.
  2. Make submittals.
  3. Architect review.
  4. Release the purchase order.
  5. Fabrication time.
  6. Delivery time.
  7. Material inventory buffer.

Get Paranoid About Procurement at the Two-Thirds Point

On most projects, long lead procurement holds steady through the middle. But at about the two-thirds point, I start to get paranoid, and I ask the project manager and project engineers to:

  • Make a complete list of every remaining item.
  • Audit the drawings. We used to do this with human intelligence only. Now you can do an AI audit too.
  • Put every remaining item on a scrum board or in the procurement log.

The end of the job is where you miss the site benches, a light fixture, or a mullion cap. Long lead items are usually tracked. The small items, like transmittals, attic stock, and manufacturer letters, usually sit with individual project engineers. So how do you get visibility into those?

The team decided on a weekly project engineer stand and deliver, with a check of the small items, plus a weekly long lead check. Another option is an AI brain, where you load the drawings and the specs and ask it to check for remaining materials. If your IT department will not allow that, sit down shoulder to shoulder with your project engineer for 90 minutes, flip the drawings page by page, and ask, do we have this?

Lock Down Deliveries With a Two-Gate System

For site logistics, I asked for the top three annoyances. The team said:

  • Big items were communicated, but things like floor tile, grout, and carpet tile were not, and everything came at once.
  • Access into the building. The hoist had just been removed, leaving a single loading dock and regular doorways.
  • Laydown space and storage.

My idea was the two-gate system we teach at the Super PM Boot Camp. Nothing gets past the second gate unless it is:

  1. Inspected, which your project engineers can do.
  2. Scheduled, so it arrives at the right time.
  3. Assigned a location on the map, so it never goes where it does not belong.

If you already have a security guard, they can send the logistics map to the foreman or logistics team as each delivery comes through the second gate. And in the afternoon foreman huddle, spend at least seven minutes on what is coming in tomorrow and where it goes. Draw it on the wall, and track the roadblocks visually.

The team pushed back, and fairly. The site is spread out, and deliveries come from every direction. So I challenged them to take the idea to their own team meeting, put the map on the wall, and decide together. Maybe a single entrance with a two-gate system, maybe something better. The team knows the site best.

How Do You Get Trades to Attend Meetings?

First, run killer meetings that add value, and clearly communicate the expectation. Be firm but fair. I had this problem as a superintendent too.

The only thing that ever fully worked for me was weekly contractor grading. Pick the top five non-subjective things that are not getting done, like logistics scheduling and meeting attendance, grade every contractor weekly, and send the report to everyone. When I was at DPR, every trade foreman was supposed to turn in a two-page weekly safety walk form before our safety team walked the job. I could never get anyone to do it. Once I put it on the grading, I started getting big packets of them on my desk.

The team was grading every six months. My suggestion was to move to weekly. Other options are to ask the trades why they do not attend, or to make a deal and follow up on it. If it still does not improve, come back to it together. That is what accountability with clarity looks like.

Zone Control and the Daily Correction System

Zone control had been an ongoing struggle, especially with prime contractors who want to come in and run. They push, we pull. I asked the team to:

  1. Do a team health score, and ask the internal team how to fix the low items.
  2. Strengthen zone control, and meet trades at the handoffs.
  3. Find a way, as a team, to be a bit more firm in a multi-prime environment.
  4. Get to the same result as a daily correction system.

The daily correction system is where the superintendent has a WhatsApp group with all the trade foremen and another with the internal laborers, carpenters, and logistics team, and sends 10 to 15 key corrective items every day to outpace the natural chaos of the site. It is not micromanaging. It is helping them see the site the way you see it. A weekly email is too slow. Then, in the foreman huddle, you ask, two of these were not done, what can I do to help?

Here is what I told the team. You deserve a supportive team. You deserve people meeting you at the handoff zones. You deserve to be listened to as the controlling contractor. And you deserve foremen and logistics folks fixing 10 to 15 items a day. That is not criticism. You deserve these things, and there is no shame in getting there. I have written more about this in The Fastest Way to Stabilize a Chaotic Job Site.

Why Fresh Eyes Work

At the end, I asked the team how I could have done it better. One of them said they loved the fresh eyes look: if we can get picked apart, it means people see where we are falling short, so take it as advice, not criticism. That is exactly the point. Our LeanTakt team supports projects this way, and you can build the same habit with monthly field walks and the right way to do a field walk.

So here is the challenge. Invite a second set of eyes onto your project this month. Ask them to start with your biggest system problems, let them ask hard questions, and then decide as a team which ideas you will actually use.

Bottom line: A fresh eyes review works when you ask for the system problems, dig in with questions, offer ideas, and then let the team decide what to do.

If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.

Want your team trained on this? See our Last Planner® System and Takt training.

On we go.

Frequently Asked Questions

What is a fresh eyes review in construction?

It is a field walk where a second set of eyes supports the on-site experts with the system components. It is about the system, not about criticizing people.

What should a fresh eyes review start with?

Ask the team for their biggest problems from a system or external factor standpoint, and listen before you suggest anything.

What does lead time include in construction?

The total time from start to delivery: hiring and contracting, submittals, architect review, releasing the purchase order, fabrication, delivery, and a material inventory buffer.

How do you get trades to attend coordination meetings?

Run meetings that add value, set a clear expectation, and consider weekly contractor grading on a few non-subjective items, shared with everyone.

What is a daily correction system?

The superintendent sends 10 to 15 corrective items a day to WhatsApp groups for the trade foremen and the internal logistics team, then follows up in the foreman huddle.

People Also Read:
The Right Way to Do a Field Walk
Monthly Field Walks
The Fastest Way to Stabilize a Chaotic Job Site

If you want to learn more we have:

-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.

Share:

    Share Link