Here’s the deal. I want to share a quick example of pull planning with AI that I can hardly believe myself. When the Aviator project started back up, one of the things we got to do was look at all of the entitlements and permitting. AI helped us turn a pile of complex documents into a pull plan in a single meeting.
Short answer: Pull planning with AI means giving an AI tool your complex documents and asking it to map every key consideration on a timeline. On the Aviator project, AI turned stacks of permitting and entitlement documents into dated stickies on our Miro board. The team adjusted them, the AI suggested questions for the designers and our permitting consultant, and in one meeting we confirmed we were cleared for March 1st.
Where the Permitting Information Came From
There is a really cool company called Cadence. They are a red tape remover, and they really help developers get things going in the city of Phoenix.
Cadence had prepared all of the shared documents for us. I am not going to show the details, on purpose, because the information is proprietary. But I can tell you they were complex. There was a lot of information, a text breakdown of all the different permit statuses, and even more complex detail behind that. Every permit is a constraint, and we needed to see all of them in one place.
How Did We Use AI to Build the Pull Plan?
We love pull planning. We have written books on pull planning. We were going into an official pull plan to find out where everything was. When we got there and received those documents, here is what I did:
- I plugged the documents into Claude.
- I copied the link to our board on Miro and gave it to the AI, so it could work on that specific board.
- I asked it to distill all of these documents and start to map everything out on a timeline.
- I told it I had already done a pre-construction timeline to get us close to March, but I needed a double check to make sure we could make all the deadlines.
What you see on the board is what came back. It created stickies for every key consideration and put dates on them. Then I asked it to put them on the timeline.
We May Already Have the Pull Plan
With just a little bit of modification, Eddie, Louise, and I think Gouty put all of these stickies in place, ready to go. After about 40 minutes of other discussion, the team said, okay, we can get into the pull plan. And we said, I am sorry, ladies and gentlemen, I think we may already have it.
| What the AI did | What the team did |
|---|---|
| Distilled all the permitting documents | Shared the board and gave the AI clear instructions |
| Created a sticky with dates for every key consideration | Modified the stickies and placed them on the board |
| Mapped everything on a timeline | Checked it against our pre-construction timeline |
| Wrote questions to vet the plan | Asked the design members and Cadence to confirm |
How Did We Vet the AI Pull Plan?
The AI also gave me questions to ask all of the design members and Cadence, to confirm that we had a clear path. We asked them, and the answers vetted the plan to the point where we had zero concerns.
We said, yes, we can hit March 1st, as shown by all of the red milestone stickies. We knew our clear path was 100 percent possible. And I am a big advocate for pull plans, but we did not have to do anything else after that. Everything was ready.
A Permanent Visual for Permitting
That board will become the permanent visual for our permitting. We will print it out and put it up on the wall, so we can track the expirations, the durations of all the permits, and the status of everything visually, the same way we track anything else that could stop the work.
It is an active file. This is how we get to tender. This is all of our permitting, and it confirms that we are cleared for March 1st. All of it came from one meeting, distilling down all of this complex information so we could control the work instead of reacting to it.
Will AI Take Your Job?
AI is not going to take your job. But it is going to help you digest so much complex information. The pull plan still needs the people. The team modified the stickies, asked the questions, and confirmed the path. AI just got us there much faster.
So here is the challenge. Take the most complex stack of documents on your next project, such as permits, entitlements, or submittals. Ask an AI tool to map the key considerations on a timeline and to give you questions to vet it. Then confirm the plan with the people who own the information.
Bottom line: AI is not going to take your job, but it will help you digest complex information, and it can turn a pile of permitting documents into a pull plan your team can confirm.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
Want your team trained on this? See our Last Planner® System and Takt training.
On we go.
FAQ
What is pull planning with AI?
It means giving an AI tool your complex project documents and asking it to map every key consideration on a timeline. The team then adjusts the plan and confirms it with the people who own the information.
How did Jason use AI to build a permitting pull plan?
I gave the AI the permitting documents and our Miro board link, and asked it to map everything on a timeline. It created dated stickies for every key consideration, and the team adjusted them in one meeting.
How do you check an AI-built pull plan?
Ask the AI for questions to vet the plan, then ask the design team and your permitting consultant. On our project, those answers left us with zero concerns.
Will AI take construction jobs?
AI is not going to take your job. It is going to help you digest complex information faster, but the team still has to adjust and confirm the plan.
People Also Read:
What Is a Look Ahead Plan in Construction?
The Difference Between Roadblocks and Constraints
Roadblock Tracking Maps
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.