Introduction – How Big Things Get Done Series

Empire State Building construction plans spread across a superintendent's table
Read 8 min

This post begins a series on How Big Things Get Done by Bent Flyvbjerg and Dan Gardner. The subtitle is The Surprising Factors That Determine the Fate of Every Project, from Home Renovations to Space Exploration and Everything In Between. Much of the information comes from a construction background, and I appreciate it very much. This is an absolutely fantastic work, and I hope you will take the time to read it.

Short answer: Big projects fail far more often than we admit, and the reason is a lack of planning. Your project will have the same number of problems either way. You can find them in preconstruction or during construction. Think slow and act fast.

Why Do Projects Go Wrong?

Think about that for a minute. Why do they go wrong? Some of this information will shock you. The book opens with a story. In 2008, California voters were asked to imagine boarding a sleek silver train at Union Station in Los Angeles and arriving in downtown San Francisco two and a half hours later for an $86 ticket. That was California High-Speed Rail. Summarizing: it would cost $33 billion and be ready by 2020.

Construction started, but the project was hit with constant delays. Plans changed repeatedly, and estimates soared to $43 billion, $68 billion, $77 billion, then almost $83 billion. As the author wrote, the highest estimate was $100 billion, and nobody knows the final cost. In 2019, California’s governor announced the state would complete only part of the route, the section between Merced and Bakersfield in the Central Valley.

Train to nowhere Original New
Completion 2020 2030 (10 years late)
Cost $33 billion $100 billion
Distance 500 miles 172 miles

What Is the Iron Law of Megaprojects?

That story isn’t a one-off. It’s common. The research database started with 258 projects and now contains more than 16,000 projects from more than 20 fields in 136 countries. Here are the statistics:

  • Only 8.5% of projects hit the mark on both cost and time.
  • A minuscule 0.5% nail cost, time, and benefits.
  • 91.5% go over budget, over schedule, or both.
  • 99.5% go over budget, over schedule, under benefits, or some combination.

Doing what you said you would do should be routine, or at least common, but it almost never happens. We put 1.5%, 10%, maybe 15% into contingency. The research shows the mean cost overrun for major building projects is 62%. And the bell curve has what the book calls fat tails: outliers hundreds of percent over target. My own experience traveling around North America and Europe matches.

Why Did the Empire State Building Succeed?

The book quotes the builders: the designs were rigorously tested, and hardly a detail was issued without being thoroughly analyzed. The architects knew exactly how many beams and of what lengths, even how many rivets and bolts, windows, and blocks of limestone. Even before it was begun, the Empire State Building was finished entirely on paper. It was estimated at $50 million and cost $41 million, 17% under budget, and it finished several weeks before the opening ceremony. The author calls this pattern think slow, act fast. Read Hurry Up and Plan: Why I Drive Hard in Pre-Construction Planning.

Why Does This Book Matter So Much to Me?

When I talk about preconstruction and the Takt Production System, these are remnants of planning systems I collected from Hensel Phelps, DPR, Okland, and others. People ask, can you show me some proof? Finally, here’s an amazing book linked to the studies.

We have to get out of our minds that it’s okay not to plan projects. I hear so-called lean experts say there’s not much use in predictive planning, or what I call target planning, and that we shouldn’t create schedules until we’re right up on the work. I disagree completely. In The Art of War, Sun Tzu said great generals win the war before going to battle, while amateurs go to war and then seek to win. General Patton, Eisenhower, and the Allied forces planned ahead the same way. Read Winning in Preconstruction!.

How Early Should Builders Plan?

Preconstruction typically happens a couple of weeks, maybe six weeks, before notice to proceed. It should happen way earlier. We need builders on months before the start. At DPR, I was on the Bioscience Research Laboratory at least eight months ahead. The general superintendent said, it doesn’t make sense for you to sit in this office and plan, go do some special projects while you wait. I kept pushing back. At Hensel Phelps, I came from a world where builders are in the office ahead of time planning. We planned that project so well with the team, and that project made me, the project executive, the project manager, and the whole team. Never let anyone talk you out of planning by saying, we’ll figure it out as we go.

What Is the Window of Doom?

Picture a project with eight major problems. Without good preconstruction planning, in wishful-thinking mode, you find those eight problems during construction, and they stop construction. The book says: think of the duration of a project as an open window. The longer the duration, the more open the window, and the more opportunity for something to crash through, including a big, bad black swan. And your team’s burn rate on general conditions keeps running the whole time.

General George S. Patton said casualties in battle result from two factors: effective enemy fire, and the time the soldier is exposed to it. The time you are exposed is reduced by the rapidity of your advance. Now picture those same eight problems, or at least seven of them, found in preconstruction. You can fix or prevent them before you go out in the field, and you have a real chance to finish on time.

Of everything I’ve shared over the years, this one thing is worth it: your project will have the same number of problems either way. You can find them during construction or before you begin. And remember Hofstadter’s Law: it always takes longer than you expect, even when you take into account Hofstadter’s Law.

So here is the challenge. On your next project, list every major problem you can find before NTP, and don’t let anyone send you to the field until you’ve looked.

Bottom line: Think slow, act fast. Finding your problems early is the key to even coming close to surviving a construction project.

If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.

Want your team trained on this? See our Last Planner® System and Takt training.

On we go.

How Big Things Get Done series:
This is the first post of the series.
Next: The Pushing Fallacies

Frequently Asked Questions

How often do big projects hit their targets?

According to the research in How Big Things Get Done, only 8.5% of projects hit both cost and time, and only 0.5% hit cost, time, and benefits. The mean cost overrun for major building projects is 62%.

What is think slow, act fast?

The pattern behind successful projects like the Empire State Building: plan rigorously up front, finishing the project on paper before construction begins, and then build quickly.

What is the window of doom?

The duration of a project is an open window. The longer it’s open, the more chances for problems, including black swans, to crash through. Finding problems in preconstruction instead of during construction keeps the window short.

People Also Read:
Get Rid of the Word Should in Pre-Construction Planning
The Art of War Reflections – Chapter 8
Recovering a Project
Pre-Construction Planning: The Five Must-Do Items

If you want to learn more we have:

-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.

Share:

    Share Link