Read 18 min

How to Actually Become a Project Manager

Here’s the deal. A lot of people think becoming a project manager means getting the title and learning the administration. That is not it, and treating it that way is exactly why so many project managers stay stuck in an office instead of genuinely leading a project.

The Partnership That Taught Me This

One of my favorite people on the planet is Ryan Young, who was the project manager on my very first project as a superintendent. There cannot be any disconnection between a superintendent and a project manager on a construction project, and I learned that the hard way.

I came into that partnership from an older, stuffier culture, not really used to genuine integration and teaming, and I spent the first three or four months genuinely frustrated. Ryan kept pulling me in anyway, staying focused on people the entire time, until I finally broke and became fully open to a transparent, integrated approach. Once that happened, we linked arm in arm. I took care of what he was worried about, and he took care of what I was worried about, and it turned into a genuinely wonderful partnership. When people tell me they are not getting along with their super or their PM, my honest advice is usually to go to lunch and actually get to know each other, because that dynamic between the two roles is absolutely crucial to how well a project runs.

Lesson One: Lead People First, Not a Title

Ryan never treated the role as administration or as a title that let him boss people around. He knew it was fundamentally about people, and he knew how to lead boots on the ground. That is the actual starting point for becoming a real project manager.

Jocko Willink’s approach to extreme ownership gets this right. If something is wrong, it is your fault, and that is genuinely a good thing, because it means you have the power to change it. Go dig into the relationship. Go work it out. Go focus on the value of the human being in front of you. From there, leadership comes down to three things, repeated constantly: clarity, training, support. Clarity, training, support, delivered shoulder to shoulder, over and over.

Dale Carnegie made a related point in How to Win Friends and Influence People, drawing on research involving hundreds or thousands of people, that somewhere between eighty and ninety percent of any role is genuinely about people, with only ten to twenty percent being the technical piece. That applies whether you are a project manager, an engineer, an architect, a foreman, or a vendor. The job is overwhelmingly about people first.

Lesson Two: Reduce Administration So You Can Actually Be in the Field

I was recently doing a field walk with a genuinely strong project team who wanted to get ahead on procurement, planning, permissions, and information, making sure the field had full kit, but they felt like they simply did not have enough time. The first fix is a real personal organization system: a working to-do list, leader standard work, time blocking, avoiding back to back meetings, and using email sparingly.

The second fix is more aggressive. We have to genuinely reduce non-value administration. If I could, I would eliminate RFIs entirely, answering questions at the source through a live design session instead, immediately, rather than routing them through a slow paper trail. I would treat submittals the same way, largely pre-selected and automatically posted rather than run through a heavy administrative process. Extensive monthly reporting, bloated project controls, and needlessly complicated pay application processes for both subcontractors and owners could all be reduced significantly too.

Watch for these signs administrative load is quietly keeping your project managers out of the field:

  • RFIs and submittals routed through a slow, multi-step process instead of resolved at the source
  • Monthly reporting requirements that consume significant time without changing any actual decision
  • Project managers who cannot remember their last full day spent physically in the field

That reduction exists for one reason. Project managers, assistant project managers, and project engineers need real time to be in the field, because the actual job is providing full kit, meaning the information and materials a foreman and crew need, inside their zone, within their Takt time window. That is the job. Everything else exists to support it.

Lesson Three: Become Ridiculously Reliable

Here is something harder to put into words, so I want you to genuinely feel this rather than just read it. There is a real difference between a forward thinking project manager who stays ahead of the game and a reactive one who needs to be reminded constantly, forgets a pay application detail, and slides into a kind of victim mode when something slips.

My wife has always had what we call object permanence in our house, meaning she can always remember exactly where something is and holds real mental context for it. A great project manager carries that same quality. People should be able to say about them, they are reliable, they always know what is going on, and they understand contextually where the project needs to be and how to actually lead it there. That reliability is not a nice bonus trait. It is close to the core of the job.

Lesson Four: Learn to See Flow, Not Just Departments

This next one is genuinely hard to explain fully, and it might be the most important shift on this list. We cannot be department focused, silo focused, or task focused. We have to be flow focused.

Niklas Modig and Pär Åhlström, in their book This Is Lean, describe this precisely, and I have had the chance to hear Modig speak directly on it. A department will sub-optimize. A silo will sub-optimize. A person handling a single, isolated task will sub-optimize, and none of that gets the information the crew actually needs to them in time. Every department, every task, and every process should be oriented toward creating flow, of information and of materials, all the way to the crew on site, so that crew can genuinely move from zone to zone to zone without friction. The single best way to develop this instinct is to genuinely study Lean thinking.

Lesson Five: Learn Planning, Not Just Scheduling

There is a meaningful difference between scheduling and planning, and this distinction has been on my mind constantly lately. Scheduling is one small piece of the picture, dates, a lock line, a sequence. Planning is where you actually make sure the crew has full kit, and everything else subordinates to that single outcome.

If I ever went back into scheduling as a career, I would insist my title be changed to planner. I also genuinely dislike the common saying that a plan is not a strategy. A good plan, with the right tactics built into it, is a strategy, one where everything is set up specifically to enable the foreman and the workers in the field. Do not just focus on the schedule. Make sure the plan produces full kit as its actual outcome, and hold to the principle that we do not start until we are ready to finish.

Lesson Six: Learn From People, Not Just Concepts

Find an excellent mentor. Figures like Patrick Lencioni, the Table Group, Simon Sinek, and Jocko Willink can serve as strong role models too, but the real advice is simpler than any book. Find somebody who genuinely leads at the level you want to lead, and model them directly. Surrounding yourself with the people you actually want to become is close to the whole secret.

Follow this pattern and you naturally stay away from drowning in administration, typing emails all day, and the disconnection that separates leadership from the field. A non-Lean company keeps leadership and the field as two separate worlds. A genuinely Lean company does not. We want project managers who are field leaders working alongside the superintendent, not stepping on toes, but genuinely understanding and supporting the flow of the entire project.

Becoming This Kind of Project Manager

If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help project managers build exactly this combination, people first leadership, real reliability, a genuine sense of flow, and the discipline to plan rather than merely schedule, all while spending real time where the actual work happens.

So here is the challenge. Look honestly at how much of your current week is spent on administration versus genuine time in the field with your foreman and crews. If the ratio has quietly tipped toward the office, that is exactly where to start reclaiming your time, one reduced RFI, one streamlined submittal, and one afternoon at a time.

Jason Schroeder said it plainly: “Clarity, training, support.” Lead with those three things, shoulder to shoulder, and the rest of what makes a great project manager tends to follow.

On we go.

FAQ

Why does the article claim eighty to ninety percent of a project manager’s role is about people rather than technical skill?
This draws on research cited in Dale Carnegie’s How to Win Friends and Influence People, which found that across a wide range of professional roles, success depended far more heavily on interpersonal skill than technical expertise. Applied to construction, that means a project manager’s relationships with the superintendent, foremen, and trade partners often determine project success more than any single technical decision.

What is the actual difference between scheduling and planning?
Scheduling refers to the dates, sequence, and lock line that make up one piece of a project’s timeline. Planning is the broader discipline of making sure a crew genuinely has full kit, meaning the information, materials, and conditions they need to complete their work, with the schedule existing to support that outcome rather than standing on its own as the goal.

Why does the article recommend reducing processes like RFIs and detailed monthly reporting?
Because time spent processing administrative paperwork is time not spent in the field, where a project manager’s core job of ensuring full kit actually gets done. Resolving questions at the source and streamlining submittals and reporting frees up real hours for project managers to be physically present with foremen and crews, which the article treats as the actual measure of the job.

If you want to learn more we have:

-Takt Virtual Training: (Click here)
-Check out our Youtube channel for more info: (Click here) 
-Listen to the Elevate Construction podcast: (Click here) 
-Check out our training programs and certifications: (Click here)
-The Takt Book: (Click here)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction IST. As the company’s owner and principal consultant, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.