If you ever come across a project that does not have a real schedule, or you get asked to recover one, I want to give you a pattern to fix a project with no schedule. This happens a lot more than you think. You will find construction companies or supervisors working on their own, good people doing their best without the experience, and you get called in to help. You probably have your own method, but this will sharpen it.
Short answer: To fix a project with no schedule, follow five steps. Start with the end date and find the path of critical flow through the phases, including site work and commissioning. Break each phase into zones and stagger them in a Takt plan. Make every trade flow and add buffers based on a risk analysis. Pull plan each sequence with the trade partners. Then run six-week lookahead and weekly work planning, and monitor the path of critical flow.
Step 1: Start With the End in Mind
Anytime we look at a production plan, we have to start with the end. A lot of people think, okay, I am right here, what is my next step? I think that is a mistake, and it will get you in trouble.
Instead, look at the stipulated end date:
- When is your substantial completion or temporary certificate of occupancy?
- What are you trying to hit so the owner can occupy the building?
- What are your liquidated damages tied to?
- What is your risk tied to?
Start with the end, and then look at the phases.
What Is the Path of Critical Flow?
When I visited Japan recently, I saw a critical chain shown on a really neat visual. You want to understand the work phase by phase: this is my next phase, the phase after that, and the phase after that. Typically, you will have more than one of these chains, so you need to analyze which one is critical.
At Elevate, we do not believe in a critical path. We believe in what is called a path of critical flow. That means you know which phases you need to flow through in order to finish from the current date. That is your path to finish, and you know which phases have to be completed on time for you to flow. That is step one: start with the end in mind, and make sure you have a complete path.
Two things are typically forgotten, and I hope you do not forget them: site work and commissioning. If you do not have a good site work sequence and a good commissioning sequence for the building, you do not have a good path to finish.
Step 2: Break Each Phase Into Zones
Next, take each phase on that path, for example rough-in, then finishes, then commissioning, and break it into zones. Go to the Takt calculator, which is free, plug in that phase of work, and find the ideal number of zones. So instead of one summary line, the calculator might show that you ideally want eight zones.
When I recently visited Japan, I learned that they finish construction projects on average about 20 percent sooner, with about half as many accidents, and they use Takt planning as well.
Break each phase out into a Takt plan, flowing with staggered starts and finishes. Do that with each phase. Now you still have a complete path, but you can see it across your zones, exactly how the phases tie together, instead of just a summary. By the time you are done, you should see buffers.
I like this because you can play with the zoning to pull the finish forward. If the plan does not work, plug it into the calculator and find a zoning strategy that pulls it in. Once you know what is most critical to finish, optimize the zoning so you have enough buffer at the end.
Step 3: Make It Flow and Add Buffers
Do not, under any circumstances, start to trade stack or trade burden.
| Do not | What it means |
|---|---|
| Trade stacking | Too many trades in one area, unnaturally, non-consensually, and unsafely |
| Trade burdening | One trade crew asked to be in multiple areas at once, so they are overburdened |
Whatever zoning strategy you use, make sure every trade can flow from zone to zone to zone. Making it flow and adding buffers go hand in hand. As you zone for flow, make sure you have the right buffers at the end of phases and at the end of the production plan.
How Many Buffers Do You Need?
You need as many buffers before the end as it takes to cover your risks. So how do you know? You look at a risk analysis from your fresh eyes meeting. If your number one risk is about 15 days, you need 15 working days of buffer at the end. That is how you know. It is based on a risk analysis, and you play with the plan until you get the right buffers.
Step 4: Pull Plan Each Phase Sequence
Once you have a path, the sequence of each phase should be part of a pull plan, meaning you worked out the sequence with the trade partners. I am giving you the basics here. Our book Pull Planning for Builders runs you through everything, and we also have pull planning kits.
Step 5: Lookahead and Weekly Work Planning
Once you have these sequences and a path to finish, start lookahead planning and weekly work planning. I like a six-week lookahead:
- Six weeks out, look for roadblocks and start making the work ready.
- In the middle four weeks, find, discuss, and remove those roadblocks, so you are ideally roadblock free ahead of the weekly work plan.
- In the weekly work plan, you and the trades commit to the detailed day-to-day activities. This is what you execute in the field, and where you manage your handoffs.
Will small things come up? Absolutely. But anything foreseeable, you want to remove in those middle four weeks, and track it visually until it is gone.
Monitor the Path of Critical Flow
From there, keep finding and removing roadblocks, and switch your focus to monitoring the path of critical flow to make sure you are on track. In our book Takt Steering & Control, there are at least 12 ways, plus four advanced options, to recover the path of critical flow properly, without hurting people or your productivity.
These are not legitimate solutions:
- Randomly adding labor or crews at the last minute.
- Working overtime.
- Throwing money at the problem.
- Bringing out materials too soon.
- Rushing, pushing, and panicking.
So here is the challenge. The next time you are asked to fix a project with no schedule or recover one, follow these five steps in order, and do not reach for overtime or extra crews until you have done them.
Bottom line: To fix a project with no schedule, start with the end, zone it, make it flow with buffers, pull plan with the trades, and work the lookahead instead of rushing, pushing, and panicking.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
Want your team trained on this? See our Last Planner® System and Takt training.
Frequently Asked Questions
How do you fix a project with no schedule?
Start with the end date and the path of critical flow, break each phase into zones, make it flow with buffers, pull plan each sequence with the trade partners, and run lookahead and weekly work planning.
What is the difference between a critical path and a path of critical flow?
At Elevate, we do not believe in a critical path. A path of critical flow shows which phases must flow, and finish on time, for the project to finish from today.
What are trade stacking and trade burdening?
Trade stacking is putting too many trades in one area unnaturally, non-consensually, and unsafely. Trade burdening is asking one crew to be in multiple areas at once.
How do you decide how much buffer a schedule needs?
Base it on a risk analysis from your fresh eyes meeting. If your top risk is about 15 days, you need 15 working days of buffer.
What should you not do to recover a schedule?
Do not randomly add labor or crews at the last minute, work overtime, throw money at it, bring out materials too soon, or rush, push, and panic.
People Also Read:
How Buffers Work in Takt Planning
What Is a Look Ahead Plan in Construction?
The Takt Production System
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.