This is the Last Planner and takt outline. If you read a white paper on the Last Planner System, you wouldn’t find this outline. But after many years of implementing it with takt, this is the one I’m most comfortable with, and it works everywhere we attempt it. Once you have the right foremen, the right phases and functional areas with foremen for each, and a rolling meeting schedule, the next step is to design your conference room, trailer, and visuals.
Short answer: Your trailer is the window to the soul of your planning. Design interaction spaces, like a work planning wall, a permitting wall, a war corner, a kitchen, a conference room, and a picture wall, so every meeting in your system has a place to meet and the visuals to discuss its agenda. The design of your trailer is just as important as the design of your building.
Why Is the Trailer the Window to Your Planning?
You could have the best plans in the world, but if you don’t have glasses to see them, it doesn’t matter. You could have the best view from your room in the world, but without a window to see it through, it doesn’t matter. Your trailer is the window to the soul of your planning. It’s really difficult to implement the Last Planner System without the right trailer environment.
From a high level, I like a trailer to have:
- A permitting wall with all your permits
- A right-to-know area for safety documentation and OSHA notices
- A family wall with pictures of the family, which I got from Hensel Phelps in the Mid-Atlantic District
- A place for the emergency action plan
- A place for orientations, preferably in the conference room
- A killer conference room and huddle room
What Interaction Spaces Did We Design in Oakland?
I have a 3D graphic that Greg Lowe helped me develop and design when I was working in Oakland, with very specific interaction spaces:
| Interaction space | What it had |
|---|---|
| Work planning wall | Weekly work planning boards, day plan boards, a whiteboard, the roadblock tracker, the meeting agenda sign, and the circle of trust |
| Permitting wall | Permits, federal and state postings, blue stake boards, and high-level project visuals for visitors |
| War corner | The inspection wall, a whiteboard, the plan for the day, and a well-stocked war table for drawing out strategic and tactical plans as a team |
| Kitchen | Stocked, clean, and organized, with healthy and fun snacks, and a place to sit down and take a break |
| Conference room | Chairs and supplies, current signs, a whiteboard, the takt plan, zone maps, logistics plan, and two TVs |
| Picture wall | Family pictures, team reminders, team events, and fun postings |
| Landing space | For anybody visiting the project |
The kitchen might seem silly or unnecessary, but I don’t think it is. In the conference room, people need to get everything out of their heads and onto the wall and the plan, because great teams follow the plan, not just the leader. Outside, we designed the staging area, entrance, craft lunchroom, craft bathrooms, hoist, and crane, with assignments between the project administrator and the general logistics foreman for maintaining site logistics, because logistics is where it’s at. See Design Your Trailer First.
Why Two TVs?
At a minimum, you need a TV that everyone can see at the front of the room. I prefer two: your schedule, the takt plan, on one, and any other visual on the other. If I want to see the procurement, the zone maps, the logistics plan, or the roadblock tracking maps, I need to bring them up at any time.
Why Put Zone Maps Under Plexiglass?
One of the biggest things I’d recommend on the wall: if you’re going to do printouts, print your floor plans by zone and put plexiglass over them. You can get plexiglass from Home Depot, Lowe’s, or any typical hardware store. Present your takt plan and visuals on the screens in your huddle systems, and then get the trade partners drawing on the zone maps: where they’re going to be and where their roadblocks are. That is the key.
Yes, trades should look at the schedule and engage with it. But where foremen really do well is when they visualize their progress by zones. If you can get foremen to identify roadblocks by zone, track progress by zone, and look at the general flow of the project by zone, you’re set.
What Goes on Each Wall?
| Wall | What to put there |
|---|---|
| Front | The TVs, probably a whiteboard, typical agenda items, and zone maps |
| Side wall | The one-, three-, or six-week look-ahead with sticky notes for pull planning, the meeting schedule, the circle of trust, an outline of the First and Last Planner systems, and day planning boards |
| Opposite wall | The delivery board, the roadblock tracking system unless it’s on the zone maps, and the team coverage board |
| Back wall | All my guides: the quality process, things to make a project fun, foreman expectations, trade partner versus subcontractor, worker huddle and foreman daily huddle agendas, and any guides for running meetings |
Read The Circle of Trust and Remarkable Interaction Spaces.
Does Every Meeting Need Its Own Visuals?
Whatever you’re going to discuss in your meeting system must have a visual environment that enables you to discuss it. The team weekly tactical, the strategic planning and procurement meeting, the trade partner weekly tactical, the foreman daily huddle, hopefully in the afternoon, the worker daily huddle, and the crew huddle each need a place to meet and visuals that let you discuss the pertinent agenda items. That takes thought, but the more thoughtfully and intentionally you organize it, the better off you’ll be. The design of your trailer, your trailer graphics, and your meeting and interaction spaces are just as important as the design of your building.
If you need help, I have guides, references, meeting schedules, and a Miro board for the typical meetings. Grab the templates or reach out and I’ll share them.
How Can You Help?
If this helped, the biggest favor you can do for me is to share it with your team, connect with me on LinkedIn, and subscribe to my YouTube channel.
So here is the challenge. List every meeting in your meeting system. Next to each, write where it happens and which visuals it uses. Any meeting without a visual is your next build.
Bottom line: When you implement the Last Planner System, design your conference room, trailer, visuals, and interaction spaces.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
On we go.
Takt and Last Planner Implementation series:
Previous: Decide on a Meeting Schedule
Next: The Strategic Planning & Procurement Meeting
Frequently Asked Questions
Why does the trailer matter for Last Planner implementation?
Your trailer is the window to the soul of your planning. You could have the best plans in the world, but without the right trailer environment, it’s really difficult to implement the Last Planner System. Every meeting needs a place to meet and visuals that let you discuss its agenda items.
What should be in a lean construction conference room?
Ideally two TVs, one for the takt plan and one for zone maps, logistics, procurement, or roadblock maps; a whiteboard; agenda items; zone maps printed by zone under plexiglass; look-aheads; the meeting schedule; the circle of trust; day planning boards; a delivery board; a roadblock tracker; a team coverage board; and meeting guides on the back wall.
Why print zone maps under plexiglass?
So trade partners can draw on them, marking where they’ll be, where their roadblocks are, and their progress. Foremen do especially well when they visualize progress, roadblocks, and the general flow of the project by zone.
People Also Read:
How to Design a Trailer
Lean Trailer Coffee & Break Area
Why Single-Wide Trailers Don’t Work on Construction Sites
Visual Area Boards
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.