How to Review a Macro-Level Takt Plan and Logistics Strategy in Pre-Construction

Macro-Level Takt Plan and High-Level Logistics Strategy: every assumption in the strategic plan goes on the wall, visualized in time and space
Read 7 min

I want to walk through reviewing a macro-level takt plan and a high-level logistics strategy early in pre-construction, when we are planning a project and trying to get it in under budget. We do these reviews in a small room in our LeanTakt office in Phoenix, Arizona, with a table, maps, and big screens for when we are on Zoom or Microsoft Teams.

Short answer: Reviewing a macro-level Takt plan in pre-construction gives you the overall total project duration, which drives your general conditions and general requirements, so you can get to budget. Check the milestones, long lead procurement, and phases. Make sure you can see the overall strategy and the path of critical flow, and check every bucket of time against a historical reference class. Put every to-do item and assumption on the wall, visualized in time and space.

Why Do You Need a Macro-Level Takt Plan?

I have to have a macro-level Takt plan, because I need to know the overall total project duration. I need that for my general conditions and my general requirements, so I can get under budget and review all of the logistics items to make sure we are ready to go.

Huge shout-out to our LeanTakt team, including Eddie, Luis, Ricardo, Nico, and everybody else who worked on this. This is so important. We have to do more macro-level Takt planning in this industry.

What Does a Macro-Level Takt Plan Show?

New to macros? Start with how to build one.

On the macro, you will see:

All of this will be adjusted. As I go through it, I am asking, do we need to check this? Is this realistic? Do we need to adjust the phase?

Adjusting Phases and Sequences in Real Time

For example, we were just talking about how the first phase of civil work actually needed to encompass two of the buildings, plus 20 feet around each one. We will access them from the back side while we move the civil work from west to east.

We went through the macro one by one, making adjustments. Oh, we need another zone. Add that to the to-do list. We need an assumption and clarification. With phase one, where are we going to get the dirt? So we have our cut-fill heat map right there, too.

We start with preliminary plans on the wall, and the walls fill up with visuals as the review goes.

Strategy, Path of Critical Flow, and Fresh Eyes

A couple of things I want to mention about the macro-level Takt plan:

  • You should be able to see the overall strategy.
  • You should be able to see the path of critical flow. Where is this flowing?
  • Every time a fresh eyes reviewer finds a to-do list item, it goes on the wall.
  • Every assumption in the strategic plan, not the production plan, goes on the wall too.

Everything is visualized, in time and space.

How Do You Check the Buckets of Time?

A macro is mainly for the strategy and the milestones, so as I go through it, I am making sure the buckets of time are complete. Is this correct? I check it with a historical reference class.

Here is an example. On the first building, our macro ends at 32 weeks. Then we ask, at a three-day Takt time, what would that be? It is somewhere around 29 weeks. At a two-day Takt time, it is about 20 to 22 weeks.

Check First building duration
The macro About 32 weeks
Three-day Takt time About 29 weeks
Two-day Takt time About 20 to 22 weeks

So I am seeing my macro, my norm-level conservative, my norm-level aggressive, and then there is even a backup. I am checking to make sure that whenever we set a milestone, it is correct. Then, when I stagger from building to building, I will know I have a correct overall total project duration.

Getting the Civil Sequence Right

Another example. When I was looking at the civil work, I knew I had to:

  1. Do the north side curb, gutter, sidewalk, and paving.
  2. Pivot to the intersection.
  3. Then do the south side, so we can always keep access through the site.

So we added those sequences into the macro. The high level is that we look at the overall strategic plan, the path of critical flow, and the overall buckets of time and milestones. We make sure that not only is each individual sequence correct, but the overall sequence is correct.

From the Macro to the Budget

This now lets me dig deep into my supporting logistics zoning, make sure my overall timeline is correct, and get the general conditions and general requirements into the budget, so we can get to budget:

  • General conditions are your staff and insurance.
  • General requirements are your logistics items.

If you want to go deeper on building this kind of plan, see our Takt Production System Masterclass. I have also written about why I drive hard in pre-construction.

So here is the challenge. Before the budget on your next project is locked, build a macro-level Takt plan with your team, check each bucket of time against a historical reference class, and put every to-do item and assumption on the wall.

Bottom line: A macro-level Takt plan, logistics maps, and a team using its genius are how you get the overall duration, the general conditions, and the budget right.

If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.

Want your team trained on this? See our Last Planner® System and Takt training.

On we go.

Frequently Asked Questions

What is a macro-level Takt plan?

It is the high-level Takt plan for the whole project, showing the milestones, long lead procurement, phases, overall strategy, and path of critical flow. It is mainly for strategy and milestones.

Why do you need a macro-level Takt plan in pre-construction?

It gives you the overall total project duration. You need that duration to set your general conditions and general requirements, so you can get the project to budget.

What is the difference between general conditions and general requirements?

General conditions are your staff and insurance. General requirements are your logistics items.

How do you check the buckets of time in a macro-level Takt plan?

Check each one against a historical reference class, and cross-check durations at different Takt times, such as three-day and two-day, before you set the milestones.

What is the path of critical flow?

It is where the work is flowing through the project. You should be able to see it clearly on the macro-level Takt plan.

People Also Read:
The Takt Production System
How Buffers Work in Takt Planning
The Integrated Production Control System

If you want to learn more we have:

-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.

Share:

    Share Link