Here’s the deal. There is a habit in short-term planning that wastes an enormous amount of a project delivery team’s time, and almost nobody questions it. We build the plan, then we build it again, then we build it again, then we build it one more time. I want to explain why that happens, why it is overprocessing at its worst, and what to do instead.
Short answer: Short-term planning in construction should build the plan once. The pull plan, done phase by phase, becomes the production plan. The six-week make-ready lookahead and the weekly work plan are filters of that plan, not new creations. The lookahead filters for roadblocks and making work ready. The weekly work plan filters for commitments at the handoffs, and those commitments go into the foremen’s hands.
Where Does the Short-Term Plan Come From?
Start with the master plan, which should be a macro-level Takt plan. From there, you pull plan phase by phase. A phase is not a duration of time. It is a geographical location with a start and an end, with its own zones.
That pull plan becomes your production plan, and the production plan is the basis for everything. It should have buffers and milestones, and it should be an achievable, coordinated plan.
The Instruction I Cannot Subscribe To
When I was first taught the Last Planner® System, the instruction went like this. Have the trades be part of the pull plan. Then have them make a lookahead plan from scratch. Then have them make a weekly work plan from scratch. Then have them make a day plan from scratch.
That is overprocessing at its worst, and I cannot subscribe to that whatsoever.
What the Rebuilding Looks Like in Practice
The problem gets worse when it is mixed with the concept of stickies. Here is the pattern:
- Somebody does a pull plan on one board.
- Then there is a separate board for the lookahead, with completely different stickies.
- Then there is another separate board with stickies just for the weekly work plan.
That last plan is not vertically aligned to milestones. It does not have flow. And it is a complete waste of time for the project delivery team.
You might say, well, at least they have stickies so they can see. Yes, but they are seeing the wrong thing. The pull plan. The pull plan. The pull plan. The pull plan is the coordination.
Filters, Not New Creations
Once the pull plan educates your production plan (your actual level three schedule, and not in CPM, because I do not believe in CPM), everything downstream becomes a filter rather than a new creation:
- The six-week make-ready lookahead is a filter, so you can IDS, meaning identify, discuss, and solve roadblocks and make work ready.
- The weekly work plan is a filter, and its filter is commitments, commitments, commitments, commitments.
All they are is filters. They are not brand new creations.
I have written more about how to filter weekly work plans from the pull plan.
| Plan | How it is made | What it is for |
|---|---|---|
| Pull plan, phase by phase | Built once, with the trades | The coordination. It becomes the production plan. |
| Six-week make-ready lookahead | A filter of the production plan | Identify, discuss, and solve roadblocks, and make work ready |
| Weekly work plan | A filter of the production plan | Commitments at the handoffs, in the foremen's hands |
| Day plan | A filter of the weekly work plan | The handoffs the project delivery team goes to hit |
What Happens in the Weekly Tactical Meeting?
What I do in the trade partner weekly tactical, the meeting you have every week with your trade partners, is very effective, and it comes down to three things:
- Confirm with each trade that their scope is still on schedule.
- Look at the critical handoffs and make sure we are still on track.
- Ask whether any trade needs to request something from another trade that they must have in order to make their commitment.
Your weekly work plan is all about commitments, and those commitments are what have to happen in the handoffs on a weekly basis.
How Do You Choose Which Handoffs to Attend?
When you get into the next week and start planning the next day, you realize you have to hit that handoff, that handoff, that handoff. As the project delivery team member over the area, you might not be able to watch every one.
Say fifteen handoffs are happening tomorrow. Ten of them are pretty typical, so you go down the line saying, you will hand off, good, you got it, you got it. Then a trade says they want some help, so that one goes on your list. Then there is a new one, so that goes on your list too. Then a critical one, and another critical one. Now, as the superintendent, field engineer, lead person, or assistant superintendent, you have four handoffs to go hit, the ones you are committed to in the weekly work plan, to make sure you are handing off successfully.
That is how it works. Then you mark them. If you have any problems, you address them in that same-day afternoon foreman huddle, so you can correct for tomorrow.
Get It Off the Conference Room Wall
The other thing I would say is get that weekly work plan off the wall. Do not keep it on the conference room wall.
This is where Toyota’s principle applies: use only reliable, thoroughly tested technology, and Lean follows the same rule. The plan has to be available to everybody. Even if you print it out so everybody has a physical weekly work plan, I am fine with that. But it has to be everywhere. You cannot have it only on stickies on a wall back in the conference room.
Everybody needs to see as a group, know as a group, and act as a group. So instead of leaving the weekly work plan static in the office, I want it in the foremen’s hands. What you can keep in the office are the roadblock boards, so you have a place to talk about roadblocks.
That is the main philosophy around weekly work planning.
So here is the challenge. Count how many times your team rebuilds the same plan from scratch. If the answer is more than once, start treating the lookahead and the weekly work plan as filters of the pull plan instead.
Bottom line: Build the plan once, then filter it.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
Want your team trained on this? See our Last Planner® System and Takt training.
On we go.
FAQ
What is short-term planning in construction?
It is the lookahead, the weekly work plan, and the day plan, all filtered from the pull plan and the production plan. I treat each one as a filter, not a new creation, so the plan only gets built once.
What is overprocessing in short-term planning?
It is having trades participate in the pull plan, and then build a lookahead plan from scratch, a weekly work plan from scratch, and a day plan from scratch. Each rebuild duplicates work that the pull plan already coordinated.
Why are separate sticky boards for each plan a problem?
Because the resulting plan is not vertically aligned to milestones and does not have flow. People can see stickies, but they are seeing the wrong thing, since the pull plan is where the coordination actually happens.
How does a superintendent decide which handoffs to attend?
Out of all the handoffs happening the next day, most are typical and can be confirmed with the trades. The ones that go on the list are where a trade asks for help, where the handoff is new, or where it is critical.
Should the weekly work plan stay on the conference room wall?
No. I want it in the foremen’s hands, even as a printout, so everybody can see, know, and act as a group. The roadblock boards can stay in the office.
People Also Read:
What Is a Look Ahead Plan in Construction?
The Integrated Production Control System
The Difference Between Roadblocks and Constraints
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.