Imagine a kinked water hose. Will the blockage get better the more water pressure you put on it, or is it more important to undo the kink? The answer is obvious. Fixing the problems in our production system is more effective than pushing workers or adding resources. That is what takt steering and control is about.
This is Part 22 of my walk-through of my book Elevating Construction Foremen. If you are just joining, start with Part 1. This part is about takt steering and control: zones and Little’s Law, the three Ms, roadblocks versus constraints, and zone control.
Short answer: Everything in construction is organized by zone. Little’s Law says you go faster with small, leveled zones built one at a time. Crew leaders watch for waste, overburden, and unevenness, remove roadblocks immediately, and help supers optimize constraints. Then they control their zone: prepare ahead, finish behind, report needs, and keep pace with the train.
What Are Takt Steering and Takt Control?
Takt steering is the steering and adjustment of the train of trades that flow through zones. Takt control is the control and clearing of the tracks ahead of the train while supplying it with needed resources. This is where we take a good takt plan and implement it in the field with flow.
Every project will be broken up into zones. A zone could be an area of a building, a section of the exterior, a run of pipe on a civil project, or a grouping of equipment. This is not just a good idea. This is how it’s done, full stop. Little’s Law, as applied to construction, says you go faster the smaller your zones are, the work in each zone must be leveled by work density, not square feet, the effort from crew to crew must be fairly equal, and you go faster building each zone in one process flow.
A takt plan is a visual schedule showing ideal production for a train of trades. It has the trades working the same long-term plan, moving in the same sequence, doing the same amount of work in each zone, going the same speed the same distance apart, getting needed resources on time, and flowing without stops and restarts.
Do not default to adding more labor, materials, and money. Brooks’s Law says adding manpower to a project that is behind schedule delays it even longer. See Brooks’s Law, Feat. Felipe Engineer.
What Are the Three Ms on a Production Line?
The three Ms are muda, muri, and mura: waste, overburden, and unevenness. More in The Three Ms.
Waste. There are eight wastes in construction: overproduction, excess inventory, transportation, motion, defects, overprocessing, waiting, and not using the genius of the team. As Paul Akers writes in 2 Second Lean, continuous improvement begins when these wastes are memorized, and the leader or worker sees waste and makes improvements to eliminate it every day.
Overburden. This shows up as workers pushed too hard or too fast, excessive overtime, too many areas, too much context switching, zone work density too high for the time given, too few people, people working beyond their training, and no breaks or buffers. We count on crew leaders to notice, prevent, or stop these. They disrespect people and won’t yield production. Even if they did, it would be wrong. We improve the system, not push people.
Unevenness. This is when work stops and restarts: defective work, roadblocks, delayed work, unleveled zones, unleveled crews, variation, and trade or zone bottlenecks. Unevenness typically comes from roadblocks that haven’t been removed and constraints that haven’t been adjusted.
What Is the Difference Between a Roadblock and a Constraint?
Words matter, and we want to signal the right action for the right word. Most references to constraints in construction are really roadblocks. The items on constraint boards will slow or stop the train if they are not removed. They are not accepted as permanent. In The Goal, Eliyahu Goldratt defines a constraint as the limiting factor standing in the way of a goal, which you systematically improve until it no longer limits you. More in The Difference Between Roadblocks & Constraints.
| Roadblock | Constraint | |
|---|---|---|
| What it is | Anything that holds up the train of trades. Temporary and removable. | A permanent or semi-permanent limitation of the project or zones. |
| Examples | RFI not answered, unfinished drawings, layout not ready, missing material or equipment, overcommitting, safety concern, work not authorized. | Production rates, crew composition, labor availability, zone configuration, site configuration, unforeseen existing conditions. |
| The signal | Remove it immediately. | Remove it if you can, optimize and improve it, then plan and work around it. |
| Who leads | Crew leaders, in Last Planner® meetings, with supers’ help. | Supers, in strategic planning, with crew leaders’ help. |
| How it’s tracked | Leading indicator: look ahead. | Lagging indicator: production data and analysis. |
Supers optimize constraints with takt planning, steering, and control by adjusting takt zones, takt time, work packaging, and sequence, leveling labor, adjusting the number of zones per Little’s Law, reducing variation, and improving standard work. All constraints should be handled before work begins, so the only things in the crew’s way are roadblocks. You know it is working when it just flows.
How Does a Crew Leader Run Zone Control?
Zone control is when you plan for, monitor the building of, and finish the zone before moving on. It is likely one of the most important considerations for crew leaders. See Zone Control: How to Manage the Speed of the Train.
- Visualize work in zones. After the huddles, work in the field with the takt plan and zone maps. Prepare ahead in the zone and finish the work behind the crew. Without zones, there is nothing to measure against.
- Report needs to the superintendent. The super should walk the zones and talk to you every day. Tell the super or the crew leader in the zone ahead about your needs.
- Finish as you go. Punch out the work daily with the super while your crew is still there, so nothing ends up on a list.
- Plan and report in the afternoon crew leader huddle. Report progress, discuss needs ahead, and measure your speed and distance within the team.
- Follow the rules. Work by zones. Punch and finish as you go. Prepare the work ahead. No going slower; if you’re behind, recover immediately. No going faster than your zone unless you are 100% finished, inspected, signed off, have trained with your buffer, prepared your next zone, and the next trade agrees.
So here is the challenge. Look at your next constraint board or lookahead. Sort every item into roadblock or constraint, and take the roadblocks on as your number one priority this week.
Bottom line: Undo the kink instead of adding pressure, then control your zone and flow with the train.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
On we go.
Elevating Construction Foremen series:
Previous: Part 21: Production Principles: Takt, Trade Stacking, and One Process Flow
Next: Part 23: Leveling Work: Production Rates, Zones, Work Packages, Labor, Materials, and Buffers
FAQ
What is the difference between takt steering and takt control?
Takt steering is the steering and adjustment of the train of trades flowing through zones. Takt control is the control and clearing of the tracks ahead of the train while supplying it with needed resources.
What is the difference between a roadblock and a constraint?
A roadblock is temporary and is always removed to create flow. A constraint is a permanent or semi-permanent condition, like production rates or zone configuration, that is improved as far as possible and then planned around.
What is zone control?
Zone control is when the crew leader plans for, monitors the building of, and finishes the zone before moving on. It keeps the crew going the same speed and the same distance apart from other trades.
People Also Read:
What Is Takt Steering & Control?
The 8 Wastes
Takt Steering & Control Book – Zone Control
Last Planner in Construction | Constraints vs Roadblocks
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.