Elevating Construction Foremen – Part 23

Elevating Construction Foremen Part 23 title graphic with a quote about leveling work, zone size, takt wagons and protected buffers, beside a photo of a worker in a hard hat holding rolled plans
Read 8 min

Imagine your college assignment is due Sunday. You grind and finish Thursday. The professor writes back: thank you, and since you are done early, I have moved up your next due date by three days. Your nap, your night out, your day at the beach, gone. Would that student ever turn in an assignment early again? No. And yet that is exactly what construction does to crew leaders day in and day out.

This is Part 23 of my walk-through of my book Elevating Construction Foremen. If you are just joining, start with Part 1. This part is about leveling work: production rates, takt zones, work packages, labor counts, just-in-time materials, and buffers.

Short answer: Little’s Law says work goes faster when it is leveled, so work like the tortoise, not the hare. Crew leaders level work by backing durations with production rates, watching takt zone size and configuration, leveling work packages, right-sizing labor, bringing material just in time, and protecting a buffer in every work package. You could be the best in your field and still be limited by any one of these.

What Does Leveling Work Mean?

Leveling work means things are even and going the same speed, distance apart, and direction. It means no spikes, no starts and stops, and no high variation. Production systems work very well when they are leveled. Here are the levers you can pull to level your work and help level the whole system. More in Heijunka: Leveling Work for Flow and Predictability.

Why Should Crew Leaders Use Production Rates?

One of the best ways to level work packages and truly understand work density within zones is to use historical production rates based on quantities. Your opinion about how long something should take is valuable and deserves to be backed up by production rates. Accurate durations let you package work into a takt wagon, the amount of work within a zone by the takt time, so the sequence and zones can be leveled. Production rates will substantiate your opinion and keep you from being pushed into impossible durations. You could be the best person in your field and still not accomplish the work if you have an unrealistic duration.

How Do Takt Zones Affect Your Speed?

Watch three things in your takt zones: the configuration of the zone and whether it lets you flow, whether each zone has an equal amount of work, and the number of zones in the phase. The smaller the zones, meaning the more zones you have, the faster you will go. There is a point of diminishing return, and we know large zones make you go slow, so the best size is somewhere in between and likely on the smaller side.

The zone outline can be a coordination between you and the team. The number of zones can be calculated with Little’s Law: takt wagons plus takt zones minus one, multiplied by the takt time, equals the duration. This works for zones in a building, on an exterior, on a site, on a run of pipe, or for a grouping of equipment. Your zone sizes will restrict or enable your pace.

Why Must Work Packages Be Leveled?

Work packages combine multiple steps in a process. One or more work packages make up a takt wagon, the work at the intersection of a takt time and a zone. Do the trades go through the zones at different sizes and speeds? No. They must move fairly leveled and at the same speed, like a train. What happens to a train if one boxcar is overloaded? It slows, stops at bridges and tunnels, and likely derails on curves. The train will only go as fast as the slowest work package.

Work packages may need to split or combine with others. Some may need two crews. If you have a small amount of work in one takt wagon, you are wasting time. If you have too much, you are slowing down the train. As a crew leader, it is your job to watch this and raise your hand if you see a problem.

How Do You Adjust Labor Counts to Level the Train?

You may need to adjust the number of trained people on your crew. I remember leveling a sequence where we had planned a four-person crew for overhead fire sprinkler installation. The work in each zone would only take a day, but the takt time the project decided on was two days. So the crew leader adjusted the crew to two people, and they stayed in a continuous flow. We want the right amount of trained people, and possibly just a little more, but not too many. You will never go faster than the productivity loss of too few people, too few of the right people, or too many people.

Why Bring Materials Just in Time?

Bringing materials just in time means getting them to the place of work just when they are needed, whether from the vendor, from a laydown, or some mix of the two. You cannot have workers waiting on materials, and you cannot have too much material stocked on the floor getting in your way. The takt rhythm gives you solid delivery dates by zone, and those dates should all have buffers to absorb supply chain delays. They are also the dates for final confirmation and six-week make-ready planning. It is the crew leader’s job to help manage this with the project team. See Just In Time Materials – Lean Series.

Lever You could be the best in your field and still be limited by…
Production rates An unrealistic duration.
Takt zones Zone sizes that restrict your pace.
Work packages Your slowest or most unleveled work package, takt wagon, or trade.
Labor counts Too few people, too few of the right people, or too many people.
Materials Your ability to get materials when and where you need them.
Buffers Not having a buffer to improve, rest, and accelerate.

Why Does Every Work Package Need a Buffer?

Here is one of the grand secrets of all constructiondom: every schedule, phase, sequence, takt wagon, and work package should have buffers. Full stop. There is nothing I can think of in life or nature that works well without buffers. Trees have buffers between them. Your heart has buffers between heartbeats. Work weeks have a weekend buffer. Try thinking of something that works well without one.

We must head toward a known and seen buffer in every work package and takt wagon. That buffer is used for cleaning, finishing, punching, inspecting, training, 5S, pre-staging materials, and generally improving how we do work. Without it, we rush from area to area without ever getting better. Watch your buffer at the end of your scope. If it is too short, increase your capacity and capability. If it is too long, talk with the project team about reducing the takt time, crewing down, or doing backlog work. Either way, monitor and protect your buffers. More in Buffers Create Flow.

So here is the challenge. Pick your next work package. Check the duration against a production rate, check that the zone’s work matches the zone before and after it, and mark where your buffer sits. If any of the three is off, raise your hand.

Bottom line: Work like the tortoise, level everything you touch, and protect your buffer.

If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.

On we go.

Elevating Construction Foremen series:
Previous: Part 22: Takt Steering and Control: Zones, the Three Ms, Roadblocks, and Constraints
Next: Part 24: Managing Production: Bottlenecks, Cycle Times, Zones, Labor Productivity, and Variation

FAQ

What does leveling work mean in construction?

Leveling work means things are even and going the same speed, distance apart, and direction, with no spikes, starts and stops, or high variation. Little’s Law says throughput times are shorter when work is leveled.

How do you calculate the number of takt zones?

Using Little’s Law: takt wagons plus takt zones minus one, multiplied by the takt time, equals the duration. Smaller zones go faster, up to a point of diminishing return.

Why should every work package have a buffer?

A buffer at the end of every work package and takt wagon is used for cleaning, finishing, punching, inspecting, training, 5S, pre-staging materials, and improving how we work. Without it, crews rush from area to area and never get better.

People Also Read:
Lean Onboarding Series – Leveling Work
Takt Leveling Production
Before Phase Planning: Work Packages, Buffers, and Multi-Train Flow
Buffers Are NOT Shared Float

If you want to learn more we have:

-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.