This post is about the pushing fallacies, continuing the How Big Things Get Done series. This is probably my favorite topic in it. Credit goes to the authors, Bent Flyvbjerg and Dan Gardner. They say projects don’t go wrong, they start wrong. I one hundred million thousand billion kajillion percent believe that. As such, we have to get better at planning projects and making sure we start out right.
Short answer: The four pushing fallacies are the need for speed, pushing makes haste, the commitment fallacy, and strategic misrepresentation. All four are false. Pushing a team creates panic and waste and extends the project. Consistent flow is what makes a team fast.
What Are the Four Pushing Fallacies?
You’ve seen owners and others do these. Now that you’ve seen them, you know to call it out. You don’t have to offend anyone, but know these are categorically not true.
| Fallacy | The belief | The reality |
|---|---|---|
| The need for speed | We’ve got to go fast and push. | Speed, speed, speed will only extend your project. |
| Pushing makes haste | A shorter deadline motivates the team to finish early. | The data does not support it. It creates waste. |
| The commitment fallacy | Get started and hook the team before planning. | Reality shows up later, and the window of doom opens. |
| Strategic misrepresentation | Misrepresent conditions to get the project committed. | You go into a bad situation, ignoring facts. |
Why Is the Need for Speed a Fallacy?
Owners and contractors say, we’ve got to go fast, we’ve got to push. This need for speed, to get the design done, to get started, to hit milestones, to finish, will only extend your project. I’ve been sharing this for a long time, and now I feel super vindicated that there’s published data.
Over five to seven years in Arizona, which is considerable, I saw CPM schedules underestimate overall duration by about 15 to 20 percent. I could track it because I investigated the same projects and called industry friends and colleagues to find out when they finished. The owner wants to undercut the duration and make people go fast, push, push, push. The CPM schedule is too short, the team gets pushed, and the project ends up late. It enters a crash landing: over duration, over budget, with overburdened resources and teams. I saw that pattern over and over.
How did I know how long those projects would actually take? We created macro-level takt plans, and on projects where we implemented takt, the plan hit the targets. Those are not funny numbers. Read Recovering, Finishing, & Crash Landing a Project.
What Happens When You Push a Team?
When you push a team, they panic, and when they panic:
- They start to batch work and context switch.
- They increase team size and have communication problems.
- They change leaders and crew composition and onboard new people, which takes time.
- They work overtime.
- Because of that and the new people, they stop installing work right the first time.
- They stop removing roadblocks because they’re busy doing rework.
The entire project spirals out of control. Read The Truth About Overtime.
Does Pushing Make Haste?
Owners and contractors think that if they shorten the deadline, rush the team, and create an impossible target, the team will be more motivated and finish earlier. This is just not true. The data does not support it. You might be thinking, I’ve moved up deadlines before and it worked. No, it didn’t. You saw people rushing around, pushing, and being busy, so it looked like more was getting done. But you were creating waste and extending the duration. That burden of proof is on you. It’s your career.
People think pushing makes you go faster because pushing makes people frantic, and when people are frantic, it looks like more work is getting done. It just means you have more waste: overproduction, inventory, motion, transportation, defects, over-processing, and waiting. Read Pushing Is the Alternative to Good Thinking.
What Makes a Team Fast?
When we had good trade flow and a really good schedule planned in takt, even with delays, we would finish on time or up to 5% early. Those are not false numbers. I’ve given representative examples multiple times. When the team has consistent flow and isn’t rushed and pushed, they can finish early. Why? Because consistency and a lack of panic create flow, and flow enables our teams to go fast. Slow is smooth, smooth is fast. The Navy SEALs were right. That’s really the only way to go fast, so we have to plan our projects with the correct total project duration.
What Is the Commitment Fallacy?
The commitment fallacy says: if I hurry up and get started and get the team hooked, they have to do the project, and that creates motivation. It’s better to get them committed than to plan ahead of time and deal with realities. That never works. The book talks about a home renovation. You start, and the flooring is bad, so you replace that. Now the walls need to be done. Now the plumbing needs to be redone. You can’t have two types of flooring, so now you do the lower stairs. And then, and then, and then, and you have the window of doom again.
What Is Strategic Misrepresentation?
Strategic misrepresentation happens when a project’s actual conditions are misrepresented to get the project started or committed to. That is 100% a bad thing to do, because you’ll likely be going into a bad situation. People say it’s one thing when it’s really another, and they ignore the facts and skip the thinking.
I love a little quote in the book: you want the flight attendant, not the pilot, to be an optimist. If somebody’s flying the plane, you don’t want them saying, well, I think this will work out. The optimists at your work might be good people, but they aren’t good for planning your projects.
What Should You Stop Saying?
Some of the worst things you’ll ever hear are tied to the pushing fallacies: add excess labor, add excess crews, work overtime, throw money at the problem, bring materials here all at once, why isn’t somebody working in this area, let’s move up the deadline, let’s just hurry up and start. Why is pushing to start bad? You shouldn’t push to start. You should push to plan and start at the right time.
So here is the challenge. The next time someone in your project meeting says “we need to push,” ask which fallacy they’re in, and bring the plan instead.
Bottom line: Projects don’t go wrong, they start wrong. Push to plan, not to start.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
Want your team trained on this? See our Last Planner® System and Takt training.
On we go.
How Big Things Get Done series:
Previous: Introduction
Next: Iterative Planning
Frequently Asked Questions
What are the pushing fallacies?
Four false beliefs about project speed: the need for speed, pushing makes haste, the commitment fallacy, and strategic misrepresentation.
Does moving up a deadline make a team finish faster?
No. People rush around and look busy, so it seems like more is getting done, but pushing creates panic, batching, rework, and waste, and it extends the duration.
What is strategic misrepresentation?
Misrepresenting a project’s actual conditions in order to get it started or committed to. It ignores facts and usually leads the team into a bad situation.
People Also Read:
Flow, Pull, & Push
What Is Crashing in Project Management?
The 8 Wastes – Lean Series
Hurry Up and Plan
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.