The Subcontractor Just Walked Off: A Step-by-Step Response

The Subcontractor Just Walked Off: A Step-by-Step Response. Does the leader look in the mirror or out the window? No problem belongs to an individual. All problems belong to the team.
Read 9 min

I hope this never happens to you, but if a subcontractor walks off your job, you should already have a plan. Here is my step-by-step response, and it starts before the problem ever hits.

Short answer: When a subcontractor walks off your job, follow seven steps. Calm down before you react. Find out why with the five whys. Immediately loop in your project manager, project executive, and attorney. Isolate the gap, putting safety, people, and respect first. Form a task force that meets on a rhythm. Find swing capacity, but only legally. Then look in the mirror, because the cause could be yours, and fix it with the whole team.

What Red Flags Should You Never Walk Past?

One of the saddest things I hear about often is, my trade partner did not show up properly, did not show up on time, and is not participating in the meeting systems, the pull planning, or the pre-construction meetings. That should never happen. If it does, our pre-construction team has a lot to fix. We have to pre-qualify and vet our trades.  Here’s what happens when trades don’t follow the takt plan. If we do not have the right trades on the bus, in the right seats, we have a massive problem. I have written more about getting the right people in the right seats.

Do not walk past these red flags before the problem ever hits:

  • They did not do the pull plan preparation.
  • They did not do the actual pull plan with you.
  • They are not doing lookahead planning.
  • They are not participating in the pre-construction meeting.

And remember, even if it looks like their fault, it could be yours.

Contract Provisions to Set Up Before You Need Them

Please work with your attorneys to go as far as you can with provisions in the contract that let you:

  • Switch players if needed.
  • Take over the materials that are already paid for.
  • Obtain and pay for materials that are on their way, if you have to switch out or supplement that trade.
  • If the trade is bonded, notify the surety right away and follow the notice-to-cure steps in your subcontract exactly, so you keep your rights under the performance bond.

I am not going to assume that everything is the trade partner’s fault. But in general contracting 101, all of us have to get the right players on the bus. I have never seen a non-performing trade or foreman situation resolve itself. And people should not be able to hold us hostage. When you think about the effect a non-performing trade has on your A players, it becomes very clear that we have to take action.

If the trade has left for good, read what counts as abandonment of a construction project.

Step What to do
1. Calm down Do not react. Call your PM or superintendent and calm each other down
2. Find out why Use the five whys until you know exactly why they left
3. Loop in legal Call your PM, project executive, and attorney right away
4. Isolate the gap Safety first, then people, then respect and notifications
5. Form a task force Swarm the situation and meet on a rhythm
6. Find swing capacity Supplement or bring in capacity, but only legally
7. Look in the mirror Find what you did wrong, and fix it as a team

Step 1: Calm Down Before You React

If this were me, my first instinct would be to react emotionally, make calls, yell, and throw my hard hat. Do not do anything I just described. It will not help. Give yourself a minute to calm down.

If I am the superintendent, my first call is to the project manager. If I am the PM, my first call is to the superintendent. We calm each other down and agree to wait a couple of minutes before we make the situation worse. Your lawyer will love you for this.

Step 2: Find Out Why

The instinct is to jump straight into solutions. I am going to do this, and this, and this. No. Find out why first. Use the five whys. Why did they leave? Because of this. Why did that happen? Because of that. Keep digging until you know exactly why. We cannot really do anything until we know. These first steps can switch order depending on the situation.

Step 3: Loop In Legal, Your PM, and Your Project Executive

This is advice that can change your career, so please listen to me on this one. Handle this the same way you would handle any people situation. Immediately call your legal group, and loop in your project manager and your project executive.

When I was a field director and project director, I had a dual role. Anytime something happened, a complaint, a claim, or a trade issue, I would immediately call HR and legal. They loved it. They said, this is exactly what you are supposed to be doing, Jason, we are here to help.

If you get a reputation for always being transparent and looping these folks in, you will get all the help you need. We all make fun of lawyers until we need one, and then we are super grateful.

Step 4: Isolate the Gap and Prioritize Safety

Next, isolate the gap. Is the situation causing an unsafe environment? Is it putting somebody else at risk? Do you need to notify another trade? Is concrete coming? What is the actual problem? Then prioritize in this order:

  1. Safety.
  2. People.
  3. Respect, and the proper notifications.

Then you can look at how to actually fix it.

Step 5: What Is a Task Force on a Construction Project?

I learned the concept of a task force while working on a large project east of Phoenix. It does not have to be negative. When there is a situation, you immediately form a task force and swarm it. It is typically the superintendent, the PM, and the project executive, plus whoever else needs to be there, maybe someone from HR or legal. If the trade partner is responsive, the task force includes the trade partner’s PM and probably the company owner too.

At a minimum, the task force meets every morning and after lunch on the situation, on a rhythm, because this is the most important thing right now.

Step 6: Target Swing Capacity, Legally

Now target swing capacity. But you have already looped in your attorney, so do not decide anything without them, because you could be violating contract provisions. Ask:

  • Do you have another trade that can help?
  • Can you supplement?
  • Is there craft labor available?
  • Is there a way to get the original trade back?
  • Can you bring capacity from another site or resource to fill the gap?

We have to do it legally. We cannot go willy-nilly and get ourselves in trouble. Once this is going, you will be heading in a good direction and hopefully able to sleep at night.

Step 7: Why Should You Look in the Mirror?

Now that you have calmed down, really look in the mirror. Did we do something wrong? How could we prevent this in the future? Are any other trades at risk of doing the same thing? This could be our fault, and if it is, we need to know.

In Good to Great, Jim Collins talks about whether a leader looks in the mirror or out the window: the mirror to see what we did, or the window to blame somebody else. Look in the mirror.

The permanent fix has to be done with the entire team. Do not do it in a silo. One of the best pieces of advice I can give anybody is that no problem belongs to an individual. All problems belong to the team, and that only works when people feel safe to speak up. Follow that, and you will be set.

So here is the challenge. Before a subcontractor ever walks off your job, review your contract provisions with your attorney, check your trades for the red flags, and make sure your team knows these seven steps.

Bottom line: When a subcontractor walks off, calm down, find out why, loop in your attorney, protect safety first, swarm it as a team, and look in the mirror before you look out the window.

If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.

On we go.

Frequently Asked Questions

What should you do when a subcontractor walks off the job?

Calm down, find out why, loop in your PM, project executive, and attorney, isolate the gap with safety first, form a task force, find swing capacity legally, and look in the mirror.

What are the red flags before a subcontractor walks off?

They skip pull plan preparation, the pull plan, lookahead planning, or the pre-construction meeting. Do not walk past those signs.

What contract provisions help if a trade walks off?

Work with your attorney on provisions to switch players, take over materials that are already paid for, and obtain materials that are on their way.

What is a task force on a construction project?

It is a small team, usually the superintendent, PM, and project executive, plus legal, HR, or the trade partner as needed, that swarms a problem and meets every morning and after lunch.

Can you replace a subcontractor right away?

Not without your attorney. Look for swing capacity, like another trade, supplemental labor, or capacity from another site, but only in a way that does not violate the contract.

People Also Read:
Cover and Move: Building a Construction Team Before the Project Starts
The Ladder of Accountability
What Is a Look Ahead Plan in Construction?

If you want to learn more we have:

-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.

Share:

    Share Link