I remember general superintendents walking my projects back in the day. They’d walk around and say, yeah, hey, good, good, blah, blah, blah. It was a milquetoast walk. Show up, pat you on the back, love you up, and that’s really all they were going to do for you. Those were bad walks, and growing up, I never had much respect for field walks because they didn’t dig into anything.
Short answer: You can’t manage what you can’t measure, and you can’t measure what you can’t see. On field walks, you can only see the project when you carry a takt plan, zone maps, and a logistics plan. That turns a pat-on-the-back stroll into a data-mining walk that leaves the team, and you, with a to-do list for next month.
Why Is Takt the Foundation for Everything Else?
Every company, field director, general superintendent, or group of superintendents I see that uses the Integrated Production Control System, tailors it to themselves, trains everybody on it, and then does field walks holding people accountable to it is making massive progress. And I know, everyone’s like, Jason, please stop talking about takt. Guys, takt is everything. It’s the foundation, the cornerstone, the keystone. It’s the hub of the wheel that all the spokes connect to. It’s the North Star. It’s not a nice tool. It is the only escape hatch we have from this mess.
Once you build projects by zones, on a takt time, on a rhythm with trade flow, everything else falls into place, and your mind starts subconsciously solving problems in that direction.
Why Did We Have to Pause and Start LeanTakt?
When Katie and I started Elevate Construction, we targeted supers, field engineers, and foremen. We wrote Elevating Construction Superintendents and started training. Nothing. No results. Not perfectly clean sites, not the results we wanted.
Then Charlie Dunn told me, Jason, you probably overestimate some of these other concepts and underestimate the fact that you had a takt rhythm on BSRL when you did the experiment of all these Lean concepts, and how much you prefabricated. Superintendents, regardless of their training, couldn’t implement without the right scheduling system, and they couldn’t prefabricate or control their supply chains without it either. So halfway through writing the other books, I told Katie we had to stop and start a company called LeanTakt.
I called David Brown, and he asked why I hadn’t already bought the website. So I did. Katie and I spent the money to start LeanTakt. I wrote the first book, and it was horrible, garbage. But it got information out there, and people corrected me. So I wrote the second version with much more knowledge from people around the industry, and we will write a third version with the LeanTakt team. We had to get the templates and research done, because we couldn’t make progress past the superintendent’s ability to schedule. I had taken for granted that we ran BSRL with a takt plan. More in Elevate & LeanTakt Principles.
What Makes the Difference Between a Bad Walk and a Good One?
Now I tell everybody in the industry to tour your projects once a month and do field walks to hold your teams accountable. And it hit me what the difference is. The reason we had garbage field walks back then was that when the general superintendent walked, we didn’t have a schedule in our hands. We didn’t have zone maps or a logistics plan. We had nothing to compare to, talk to, or critique. My buddy Weston Wolsey, a field director at Okland, told me, Jason, never let your people go out in the field without their schedule, at least their three-week lookahead. I love that.
When I walk projects, the walks work because we are looking at data. If I walk without a schedule, what am I going to talk about? People talk about what they can see. I would love to sit back with a bag of popcorn and watch a group of superintendents take a 76-page CPM schedule out to the field to analyze anything. They ain’t gonna do nothing. I want to see that plan on one page, those zone maps on one page, and that logistics plan. See How To See Your Project On One Page.
| The milquetoast walk | The walk with a takt plan | |
|---|---|---|
| What’s in your hands | Nothing to compare against. | The takt plan on one page, zone maps, and the logistics plan. |
| The conversation | “Good, good,” a pat on the back. | What about that buffer? When is that coming? Is permanent power on? This trade is failing; how do we support you? |
| How long it takes | A quick lap. | An hour and a half to two and a half hours of digging. |
| What the team leaves with | Nothing of substance. | Helpful information and to-do assignments due before the next walk. |
| What happens next | Nothing changes. | The team maintains, improves, and uses its systems. |
What Happens on a Walk That Mines Data?
When I walk Petticoat-Schmitt, High Street, or Saunders projects, I can go on and on, there is a takt plan, and we have it in our hands. Well, what about this? What about that buffer? Here’s what we can do with this. This trade partner is failing, here’s how we can support you. We are mining data. Those walks are pregnant with meaning. We leave the project team with so much helpful information, and they leave us with to-do assignments we both know have to be done in a month when we walk again.
So they maintain their systems, improve them, upgrade them, use them, and respond to real-time data they can see. You’re going to have garbage, stupid field walks if you don’t have a takt plan. For how to run the walk itself, see Monthly Field Walks.
Can You Manage What You Can’t See?
You can’t manage what you can’t measure, but you can’t measure what you can’t see. Tailor that to field walks: you can’t manage what you can’t field walk, and you can’t field walk what you can’t see. You can only see it when you implement the Takt Production System with the right visuals. It is the key. All other success surrounds it.
So here is the challenge. Before your next field walk, print the takt plan, zone maps, and logistics plan on one page each. Walk with them in hand, ask about every buffer and delivery, and leave with assignments due before the next walk.
Bottom line: Your field walks are only as good as what you can see, so carry the takt plan and the visuals every time.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
On we go.
FAQ
Why do so many field walks accomplish nothing?
Because the leader walks without anything to compare against: no schedule, no zone maps, no logistics plan. People talk about what they can see, and without data there is nothing of substance to talk about.
What should you carry on a field walk?
The takt plan on one page, the zone maps, and the logistics plan, or at least the three-week lookahead. With those in hand, you can ask about buffers, deliveries, permanent power, and trades that are struggling.
How long should a good field walk take?
A good walk now takes me an hour and a half to two and a half hours, because the team is digging into real data and leaving with to-do assignments for the next month.
People Also Read:
The Right Way to Do a Field Walk
Suggestions after a Lean Field Walk
On One Page!
Project Success 101: IPCS – The System
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.