I’ve decided to do a little reroute in this series. Before going through each meeting in the system in detail, we’re going to start with the strategic planning and procurement meeting. I’ve covered some of this in the past and in the books, but it bears repeating, because we need to talk about how and when we create our look-ahead formats, pull plans, and weekly work plan formats, and what that cycle of creation really looks like.
Short answer: The strategic planning and procurement meeting is a weekly project team meeting where you update the takt plan, check production, budget, milestones, and buffers, review the procurement log three to 12 weeks out, and take steps to correct anything late. Then you email the current plan to trade partners. The GC sets what has to happen, and the last planners figure out how.
Who Attends and When?
As part of the Last Planner cycle, we’re trying to get the plan from the first planners to the last planners. This meeting is designed for the project team to look at the overall strategy of the project and make sure resources are aligned with it. It’s held weekly on the cycle. I prefer Mondays, but you can do it whenever you want. It includes the superintendents, project managers, project engineers, and field engineers, unless they’re busy, and the scheduler if applicable.
| Agenda item | What happens |
|---|---|
| Positive shout-outs | Start positive |
| Takt plan | Update and review it, refine takt sequences from pull plans |
| Procurement log | Update and review it, with long-lead items tracking to the right dates |
| Look-ahead | Look three to 12 weeks out and discuss major roadblocks |
| Report out | Email the current plan to the trade partners |
You need your conference room space, a whiteboard, and TV screens to pull up the takt plan and the procurement log.
What Do You Look for in the Takt Plan?
When I look at the takt plan on the screens, I’m looking for four main things immediately:
- How am I doing from a production standpoint?
- Is the overall budget for the project still correct according to how we estimated it, and are my end dates, milestones, and deadlines tracking?
- Do I have any rework, and are we setting up proper quality pre-construction meetings?
- Do I have any schedule creep? I’ll look at my buffers and milestones.
You can also dig into roadblocks, key deliveries, team health and how well people are buying into the plan, buffer management, how inspectors are working with the system, and cranes, forklifts, and hoists according to the takt plan. If you have the right backbone and strategy, and your critical flow path is being managed well, then take the time to make sure materials are tracking to the preparation dates. See The Procurement Log. You Are Not Doing This Right.
Do We Have What the Strategy Needs?
The key question in this meeting: if the overall strategy is working, do we have the crews, the equipment, the tools, most importantly the materials, and the permissions? That’s why the project engineer and project manager must be in this meeting. Look at your procurement log’s long-lead items. Is anything tracking behind, not only long term but over the next three to 12 weeks? If it is, take steps to correct it. Let me say that again: if it is, take steps to correct it. I’m convinced we don’t take enough time to correct late procurement.
| Late item | Steps you can take |
|---|---|
| Submittals | Expedite them, make it easier on the trade partners, move them up in the schedule, swarm the reviews |
| Design reviews | Ask designers for help, level their work, show them visually why it matters, give notice ahead of time, hold a Bluebeam review session or review in their office |
| Materials | Expedite, visit the shop, move up in the production line, supplement the contractor, take over shipments |
| The schedule | Use some of your buffer |
What Questions Should You Ask?
I have these as a guide if you want it:
- How is production going? Is it on track today or this week?
- Is work for next week planned well enough?
- Do we still have enough buffer for the work?
- Where are we in relation to the end date?
- Do we still have the right percentages of flow?
- What preparation steps are important now to prepare work for the future?
- What roadblocks need to be removed or absorbed? Is work being made ready?
- Are separate phases on track to support each other?
- Is the schedule networked to create a complete plan?
- Is work pushing into problematic weather times?
- Are current production rates and task cycle times projecting correctly throughout the schedule?
What Goes Out After the Meeting?
When you’re done, you should have enough information to distribute to the entire project team: the current takt plan, the current takt zone maps, the current logistics drawings and any updates, the contractor grading summary, a monthly narrative if applicable, and any new planning or changes. It goes out in an email to the trade partners, and it’s the first thing they see. In the trade partner weekly tactical, the look-ahead planning and the weekly work planning come from this. Ad hoc pull planning meetings are looped into the takt plan as part of this meeting. The look-aheads, weekly work plans, and day plans are derived from and vertically aligned with the information in this meeting.
Why Can’t the GC Skip This?
The purpose is to enact long-term strategic planning, so the team can check, manage, and update the takt plan, refine takt sequences from pull plans, and keep procurement tracking to the right dates. It sets up the overall strategic plan from command, and because we don’t command-and-control people, it’s then scaled to the trade partners in the trade partner weekly tactical.
You can’t enable the trade partners and last planners until they know what they’re doing. Then they can figure out how. That’s what everyone fails to understand. You don’t go to the trade partners and say, what do you want to do? No. General contractor, that’s your job. The overall strategic plan and the milestones need to be clear, refined in that meeting, and emailed out. Then the last planners can begin their communication, collaboration, commitment, and execution of short-interval milestones. Read A Stable Procurement.
I love Boot Camps, and we’ve done them often enough now that we’re really good at them.
So here is the challenge. Pull up your procurement log at your next Monday meeting. Find one item behind for the next three to 12 weeks, and pick one step from the list above to correct it before the meeting ends.
Bottom line: Set the strategy, align procurement, and email it out, so the last planners know what before they figure out how.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
On we go.
Takt and Last Planner Implementation series:
Previous: Conference Room, Trailer, & Visuals
Next: The Trade Partner Weekly Tactical
Frequently Asked Questions
What is the strategic planning and procurement meeting?
A weekly project team meeting, ideally Monday, with the superintendents, project managers, project engineers, and field engineers if available. It’s where long-term planning takes place, the master schedule is updated, work is made ready for the look-ahead, and procurement is aligned to the overall strategy.
What is the agenda for the strategic planning and procurement meeting?
Positive shout-outs; update and review the takt plan; update and review the procurement log; look three to 12 weeks out and discuss major roadblocks as part of the look-ahead; then report out with an email to trade partners.
What can you do about late procurement?
Expedite submittals, move them up in the schedule, swarm the reviews, ask designers for help, hold a Bluebeam review session or review in their office, visit the shop, move the order up the production line, supplement the contractor, take over shipments, or use some of your buffer.
People Also Read:
First Planner System – 10 – Procurement
What Is the Biggest Delay in Construction? Material Procurement!
Short Ramp, Strong Start: Macro Takt & Procurement
The Remaining Buffer Ratio
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.