A broken pull plan is one of the worst things that can happen on a project, because if we mess up the pull plan, everything else is messed up from there. If you are having trouble in the first couple of weeks of a phase, it almost always comes back to the pull plan. Let me tell you why pull plans break, how pull planning should go, and exactly what to do to recover.
Short answer: To recover from a broken pull plan, first observe: walk the zones and see where you really are. Then create proper zones in a time-by-location format, re-pull plan by zone with prepared trades, and engage the system with a norm-level production plan, six-week make-ready lookahead, weekly work planning, and zone control. Most pull plans break because the areas are too large, the trades were not prepared, there were no zones, and no buffers were gained.
Why Does a Pull Plan Go Wrong?
Typically, a pull plan goes wrong for one of these reasons:
- The trades were not prepared.
- There was a massive activity or trade bottleneck that nobody saw.
- The durations were unrealistic.
- We trusted the pull plan over a reference class.
- We were pulling too large of an area, instead of looking at it through zones.
- We did not look at logistics.
- We did not run the calculator ahead of time or identify zones.
I can already tell you that if your pull plan took three to eight hours, it is wrong.
How Pull Planning Should Go
Every project should have a start milestone and an end milestone. Each phase should be a geographical location with its own zones, through which a train of trades flows. Other phases can run at the same time, but a phase is a geographical portion of work.
Before that phase happens, the timing looks like this:
- About four months out, we do pull plan planning. This is where we get all of the trades’ information.
- About three months out, we actually do the pull plan. Yes, three months.
For mega projects or complex projects in the Takt Production System, start with the macro. You calculate it, which can take days or at most a couple of weeks, and then you have your path to finish all the way to the end milestone. That lets you plan just ahead of each phase, so pre-construction is not overwhelming. You are not trying to build a level three or level four schedule up front, which is why I dislike CPM so much.
If you pull plan a phase properly, it will pull forward, and you will gain buffers without ever shortening a trade’s duration.
Here is a point I have to make. All known roadblocks and constraints that show up on a project, with the exception of something like a pile of dirt in the way, a failed inspection, or a bunk of plywood in your way, have a root cause in an improperly done pull plan. So treat the pull plan like a phase gate. In it, you coordinate not only the sequence in your first zone, but also the pace and the buffers in the phase.
How Do You Run a Pull Plan by Zone?
Here is how we run a pull plan. We go through it in depth in our books, our videos, and at the Super PM Boot Camp.
- Set the conditions of satisfaction: the overall milestones, the sticky format and color, and the rules of the pull plan.
- Do the zoning first, based on the Takt calculator. We do not pull plan large batch areas. Instead of pulling a whole floor, we pull plan just one zone.
- Work the pull plan forward to the milestone. The forward pass creates the sequence of what the job needs.
- Run it back by asking each trade what they need, at least two needs per sticky, filled out in front. The backward pass makes sure we accommodate what the trades need.
- Look for phantom or missing activities. If you are doing it right, you will find some, and without them the sequence would have been wrong.
- Cascade the sequence through the other zones. A similar zone, leveled by work density, has the same overall sequence.
Remember that the end of that first zone is only a sequence milestone. The overall phase milestone comes later. Once your pull plan is cascaded through the zones, you will always gain buffers if you have done it right, and now you have optimized the phase.
As it cascades, that plan becomes your norm-level production plan. You will know it is a norm because it is usually on a one-, two-, three-, or four-day Takt time, and you will always gain buffers at the end of the overall production plan.
The Four Most Common Pull Plan Failures
| Failure | What happens |
|---|---|
| The areas are too large | Because of Little's Law, pulling areas that are too large automatically extends the overall pull plan |
| No preparation | No pre-planning sheets and no proven production rates from the trades, so everyone comes in blind and wings it |
| Not pulling by zones | The biggest problem in the industry. The zones are never cascaded either |
| No buffers gained | The phase never pulls forward, so there is no protection |
How Do You Fix a Broken Pull Plan?
So those are the problems. Here is what I would do to fix it:
- Look at the condition of the pull plan and your current production plan. My biggest tip is to go out in the field and walk the zones, hopefully you have zones, and understand exactly where you are.
- Create proper zones, and break everything out in a time-by-location format.
- Re-pull plan if you have to. Do it by zone. Get all of the trades in the room, be super prepared, and map out a realistic sequence.
- Create your norm-level production plan, start your six-week make-ready lookahead to find and remove roadblocks, and start your weekly work planning, both as filters. Then start zone control on site.
Zone control means that every time trade partners hand off from zone to zone, you go out and walk the field. Make sure that handoff happened. Then start working the system.
Why Pull Planning Is So Often Done Wrong
Pull planning is done incorrectly very often because people are taught wrong. Our books Pull Planning for Builders, The 10 Improvements to Lean Production Planning, Takt Planning, and Takt Steering & Control walk you through all of this in a visual manner. We also sell pull plan kits, and we have the information free in the toolbox on our website, because we are not here to try to extract money from you. And our LeanTakt team is always here if you want help planning and executing your project, or if you need pull plan training.
I am not trying to make you scared. But in all reality, if the pull plan is wrong, there is nothing that will work in the Last Planner® System after that.
So here is the challenge. If your pull plan is broken, do not keep working it. Walk the zones, rezone the work, re-pull plan by zone with prepared trades, and then engage the system.
Bottom line: If the pull plan is wrong, nothing after it will work, so pull plan by zone, cascade it to gain buffers, and fix a broken one by observing, rezoning, re-pulling, and engaging.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
Want your team trained on this? See our Last Planner® System and Takt training.
On we go.
Frequently Asked Questions
How do you recover from a broken pull plan?
Observe by walking the zones, create proper zones in a time-by-location format, re-pull plan by zone with prepared trades, and engage the system with lookahead planning, weekly work planning, and zone control.
Why do pull plans go wrong?
Usually because the areas are too large, the trades were not prepared, the work was not pulled by zone, and no buffers were gained.
When should you do a pull plan for a phase?
Do pull plan planning about four months before the phase, to gather the trades’ information, and the pull plan itself about three months before.
What are the forward and backward passes in a pull plan?
The forward pass creates the sequence of what the job needs. The backward pass asks each trade what they need, at least two needs per sticky, so the sequence accommodates them.
What happens if the pull plan is wrong?
Nothing in the Last Planner® System will work after that. Almost every known roadblock and constraint traces back to an improperly done pull plan.
People Also Read:
How to Fix a Project With No Schedule: The Real Method
What Is a Look Ahead Plan in Construction?
How Buffers Work in Takt Planning
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.