If I took over your job site tomorrow, here is what I would do first. Taking over a job site follows the same pattern no matter what project it is or where I go. You are probably a better builder than me, but the one thing the industry could learn from me is to be completely stubborn about respect and stability. My gift to the industry is my stubbornness for respect and stability, and everything else follows from that.
Short answer: Taking over a job site starts with people. In the first hour, I check the human systems: bathrooms, handwashing, the lunch area, and how clean the site is. In hour two, I ask the foremen what is in their way. On day one, I reset respect. On day two, we clean everything and reset safety. On day three, I install the huddles. Then I organize everything by location and build a plan to finish.
I have more than 30 years in the industry, most of it as a craft worker, then foreman, field engineer, assistant superintendent, superintendent, project superintendent, senior superintendent, general superintendent, and field director. I did not go to college. I am not a consultant or an influencer. I am a superintendent doing this to help the industry.
| When | What I do |
|---|---|
| Hour 1 | Check the human systems on site |
| Hour 2 | Walk the field and talk to the foremen |
| Day 1 | Reset respect |
| Day 2 | Stabilize: clean everything and reset safety |
| Day 3 | Install the afternoon foreman huddle and morning worker huddle |
| Week 1 | Organize everything by geographical location |
| Week 2 | Build the plan to finish and work the system |
Hour 1: Check the Human Systems
Whether a project is behind or not, in the first hour of walking the site I am looking at the human systems:
- I open up the bathrooms. Are they clean?
- Is there a place for the workers and foremen to wash their hands?
- Is there a trash can there?
- Is there a respectful lunch area?
- Do the communication systems reach all the way to the field workers?
- Is the jobsite clean and organized?
- What is the morale like?
A really cool general superintendent at Hensel Phelps once gave me a document called Signs of a Project in Trouble, and it is one of the coolest documents I have ever found.
Is a Dirty Job Site a Project in Trouble?
Yes. If the site is not clean, I automatically know the project is failing. You might say, Jason, you cannot know that. But the truest thing in all of construction is that if the project is dirty, that project is in trouble. If the jobsite is dirty, the project delivery team has no control of the environment and rhythm, and the field and the trade partners are left alone to struggle.
Hour 2: Why Talk to the Foremen First?
In hour two, I walk the field, with my PPE, and talk to the experts: the foremen. I ask them:
- What is in your way?
- What has held you up?
- What are you feeling on this project?
- What systems are broken?
- What do you actually need to do your job?
This is the most value-added thing I do on that first day. The foremen know exactly what is needed. It is my job, and all of our jobs as general contractors, to provide four things. This is the simplest framework on earth:
- A remarkable environment that is clean, safe, and organized.
- Rhythm, so the train of trades can actually flow together.
- Integration and coordination.
- Resources and on-time payments.
The foremen will tell me what is not working, and it is my job to get it to them.
Day 1: Reset Respect First
On day one, I reset respect. Anything I found in the human systems, I fix right away:
- Good bathrooms and handwash stations.
- A good lunch area.
- A morning worker huddle and respectful communication.
- A smoking area.
- Good wayfinding signage.
- Good onboarding and orientation systems.
I will schedule my first craft barbecue, and I will take my best crew out to crab legs at the casino right away. Even if I cannot get all of it set up in one day, all of it will be ordered on the first day. I take care of the humans first.
Day 2: Stabilize and Reset Safety
On day two, we stabilize and reset. That means we clean. And I have a higher tolerance for holding people accountable. I have shut down entire jobs, lovingly, in companies that are not mine and where I had no authority, and when the superintendent pushed back, I pushed back as well.
We clean everything on the job, perfectly. We organize everything. And we reset safety for everything: everybody wearing their glasses and hard hats, filling out their pre-task plans, fall protection, everything 100 percent. The best field directors and superintendents will agree with me. You cannot do anything for recovery unless it is clean first.
Day 3: Install the Huddles
On day three, I install the most effective meeting structure ever:
- An afternoon foreman huddle the day before.
- A five- to seven-minute morning worker huddle with all of the workers, in the area on their way from the parking lot to the project site.
That starts a short-cycle planning system with a feedback loop right away. We talk about what we need the next day from a planning perspective, and we stop the line. We are not going to start the next day until we are absolutely ready to finish.
Week 1: Why Organize by Location Instead of Scope?
One of the most detrimental things in construction is organizing everything by scope, scope, scope. Stop doing that. Everything on the project site should be organized by location: the schedule, your visuals, your systems, your meeting structure, your organization chart, and your work packaging. You want people supervising by geography, by building, and by area. Your construction work areas, construction work packages, engineering work packages, procurement work packages, and installation work packages should all be done by location too.
Recently, I was working with a project team that had everything grouped by train of trades. I said no, break it down in this order:
- Overall program.
- Project.
- Building.
- Phase.
- Areas.
- Zones.
- Micro zones.
I am going to organize the production plan, the procurement system, the procurement log, and the org chart by geographical location immediately. It is not going to work any other way.
Week 2: Build the Plan to Finish
By week two, I will have a plan to finish. I wrote about exactly how to do that in How to Fix a Project With No Schedule. Then you work the system, lockstep, from there.
The Integrated Production Control System has five books: Elevating Pre-Construction Planning, Takt Planning, Takt Steering & Control, Pull Planning for Builders, and the IPCS Guidebook. If you want to learn the system, go to the Super PM Boot Camp. And if you ever need help, we have resources that can help you boots on the ground, and we can do remote virtual field walks. I never want to just put out information without being here to help.
So here is the challenge. Walk your job site tomorrow as if you just took it over. Open the bathrooms, check the lunch area, and ask the foremen what is in their way. Then fix the human systems before you touch the schedule.
Bottom line: Taking over a job site starts with taking care of the humans, making it clean and stable, installing the huddles, and organizing by location before you work the system to finish.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
Want your team trained on this? See our Last Planner® System and Takt training.
On we go.
Frequently Asked Questions
What should you do first when taking over a job site?
Check the human systems in the first hour: bathrooms, handwashing, trash cans, the lunch area, communication, cleanliness, and morale. Then talk to the foremen.
Is a dirty job site a sign the project is in trouble?
Yes. If the jobsite is dirty, the project delivery team has no control of the environment and rhythm, and the trades are left alone to struggle.
What does a general contractor owe the trades?
A clean, safe, and organized environment, a rhythm so the trades can flow together, integration and coordination, and resources and on-time payments.
What meetings should you install on a job site you take over?
An afternoon foreman huddle the day before and a five- to seven-minute morning worker huddle, so you start short-cycle planning with a feedback loop right away.
Why organize a project by location instead of by scope?
Because people should supervise by geography, by building, and by area. Organize everything from the program down to micro zones by location.
People Also Read:
How to Fix a Project With No Schedule: The Real Method
Clean, Safe, and Organized: The Foundation of a High-Performing Job Site
The Right Way to Do a Field Walk
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.