Pre-Functional Testing Explained Step by Step

Pre-Functional Testing Explained Step by Step: once all of the individual component parts are working, then we test it together.
Read 6 min

I want to explain pre-functional testing step by step, but for field builders. If you are a commissioning agent who wants every detail, this is not that post. This is for builders who want to know what we need to do to enable the trades and the commissioning agents. If you start pre-functional testing properly, with good preparation, the rest of the process can go well, as long as we are building on a rhythm with a Takt plan.

Short answer: Pre-functional testing confirms that each piece of equipment is properly installed, connected, and ready for testing before the whole building is tested together. The commissioning agent prepares a pre-functional checklist from the specs, historical documents, and manufacturer information. Field builders complete it floor by floor during interiors, checking the duct, piping, controls, power, and bracing, then run point-to-point controls testing, so later testing of the whole building can go well.

What Is a Pre-Functional Checklist?

A pre-functional checklist is an installation and startup verification checklist. It confirms that equipment is properly installed, connected, and ready for testing.

Think of it like a human body. Before I test whether my whole body works, I need to make sure my finger works properly, and my hand works properly. Once my fingers, hands, arms, shoulders, stomach, brain, lungs, and all of my other systems have been individually tested, then I see if I work as a human being. Pre-functional testing is checking each finger. Once all of the individual component parts are working, then we test it together.

These checklists are crucial. They are typically prepared by the commissioning agent, from the specs, historical documents, and the manufacturer’s information for each piece of equipment. We love checklists, and checklists love us.

Where Does Pre-Functional Testing Fit in the Schedule?

In the schedule, the interiors run floor by floor: floor one, two, three, four. After that comes the overall commissioning effort. Pre-functional testing happens inside the interiors, floor by floor, as we install:

  • Fire sprinklers.
  • Priority walls.
  • Overhead duct.
  • Overhead mechanical equipment.
  • Any other equipment.

What Does the Pre-Functional Checklist Check?

Once the equipment is up, we hook everything up and check it:

Hookup What the checklist confirms
Dry side The duct connection is connected, sealed, and insulated
Wet side The hydronic piping, including heating hot water and chilled water, is hooked up to the equipment
Controls The controls are hooked up
Power The power is hooked up and wired properly
Bracing The equipment is braced properly

Then there is a whole list of other checks, done according to the manufacturer’s specifications, so we know the equipment is working properly. So many things can go wrong:

  • The fan could be turning in the wrong direction.
  • It could be wired improperly.
  • It could be braced improperly.
  • There could still be safeties on.

Why Should You Start Pre-Functional Testing Early?

Your commissioning agent may say, we will come in a little bit later. That’s exactly why commissioning must start on day 1. And you need to say, no, we need to be driving this. There is a milestone for having all of your pre-functional testing done on an individual basis, and then the point-to-point. If that milestone slips, it becomes a constraint on everything that follows.

Point-to-Point Testing and Controls

Point-to-point is where you do controls testing and communication testing inside your control system, from the equipment itself back to your control system hubs. On the last building I did, we tied the equipment to the JACE (the Java Application Control Engine, the controller that collects the equipment’s points), tied the JACEs together, and then tied them into the overall building automation system.

Make sure this milestone tracks with your integrated testing throughout the building, and with permanent power and internet. Do not forget the internet. If you are controlling or monitoring your building automation system remotely from another location, you need an internet connection. I wrote about how all of this comes together in Whole Building Commissioning: The Complete Process.

Pre-Functional Now, Test Everything Together Later

Think of it like this. The production plan for the interiors does the pre-functional checklist and pre-functional testing, so that later in the schedule you can test everything together. I know that is a simplistic way to look at it, but it works.

Ask a lot of questions. Understand the process. Ask your trade partners, partner with them, ask what they need, and track the milestones together. If you want to go deeper on keeping it all flowing, see our book Takt Steering & Control.

So here is the challenge. On your next building, put the pre-functional checklist and point-to-point milestones into the interiors production plan, floor by floor, and ask your commissioning agent to start early with you.

Bottom line: Do the pre-functional checklist and testing floor by floor during interiors, on a rhythm, so you can test everything together at the end.

If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.

Want your team trained on this? See our Last Planner® System and Takt training.

On we go.

Frequently Asked Questions

What is pre-functional testing?

It confirms that each piece of equipment is properly installed, connected, and ready for testing before the whole building is tested together.

Who prepares the pre-functional checklist?

The commissioning agent typically prepares it, from the specs, historical documents, and the manufacturer’s information for each piece of equipment.

What does a pre-functional checklist check?

The duct connection, the hydronic piping, the controls, the power and wiring, and the bracing, plus other checks from the manufacturer’s specifications, like fan direction and safeties.

What is point-to-point testing?

It is controls and communication testing from each piece of equipment back to your control system hubs and into the building automation system.

When should pre-functional testing happen?

Floor by floor during interiors, as early as possible, so the whole building can be tested together later in the schedule.

People Also Read:
Whole Building Commissioning: The Complete Process
Field Quality Checklists
The Takt Production System

If you want to learn more we have:

-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.