Whole-Building Commissioning: The Complete Process

Whole-Building Commissioning: The Complete Process: the main thing you're tracking is milestones, milestones, milestones, and interconnections.
Read 8 min

I want to walk through whole building commissioning for a typical commercial building, and put all of the individual component parts together. I am going to attack it the way I attack everything: by starting at the end of the schedule.

Short answer: Whole building commissioning brings every system together at the end of the job. Work back from substantial completion with a commissioning pull plan. First get permanent power, ductwork and hydronic piping, a complete controls network, and IDF rooms with internet in place. Then run vertical point-to-point testing, test and balance, functional performance testing coordinated with fire alarm testing, integrated systems testing, and final acceptance testing with the AHJ and engineers.

Start at the End of the Schedule

Start with substantial completion. You have to know what substantial completion means. I wrote about that in Substantial Completion vs Final Completion Explained. Look at substantial completion and final completion, and work back with what is basically a commissioning pull plan to find out what the process before them needs to be.

This is typically started too late. It depends on permanent power, internet, controls, and your building systems being up, but mainly on power, because you have to have power for your air handlers to come online. Every one of those is a constraint you need to see coming.

What Do You Need Before You Can Commission a Whole Building?

To commission the entire building, you need these systems in place:

  1. Permanent power. That means permanent power connected to your entry rooms on the lower level, and feeders pulled up to your other electrical rooms and terminated to panels, so you can energize floor by floor and energize the lighting control panels.
  2. Ductwork and hydronic piping. You need your supply, return, and exhaust duct, plus your heating hot water, chilled water, and domestic (potable) water piping, brought up through the chases and accessible everywhere.
  3. A complete controls network. Your building automation system has to be connected from a control standpoint from bottom to top.
  4. IDF rooms and internet. Your intermediate distribution frame (IDF) rooms have to be built out beautifully, with internet connectivity, racks in, and servers up and running.
  5. Gas and ancillary equipment. That includes your central utility plant if you have one, water heaters, and any other ancillary equipment.

Once all of that is running, you should have air handlers blowing hot and cold air throughout the building, in a clean, sealed environment, with a complete working system.

Why Do the Controls Have to Connect Every Floor?

Pay attention to this one. When you put the building under building automation system control, you need all of the floors talking to each other. Typically, you cannot get the air handlers in hand, blowing cold air, unless all of the floors are interconnected. And typically, they are not, so you have to pay the controls contractor to run a temporary vertical line connecting all of your systems. For full commissioning, the controls have to connect the whole building, which means those IDF rooms have to be built out.

What Is the Whole-Building Commissioning Testing Sequence?

Here is the sequence once the systems are up:

  1. Vertical point-to-point. You have already done point-to-point on each floor. Now you do it vertically, to make sure your communication systems and controls are talking to each other throughout the building.
  2. Test and balance. This makes sure your air flows and water flows match the design.
  3. Functional performance testing. The air handlers are running, the exhaust fans run when needed, and your commissioning agent goes through and tries to fail the entire system.
  4. Integrated systems testing. You test everything together as part of functional performance testing.
  5. Final acceptance testing, through the AHJ and the engineers.
Test What it checks
Point-to-point (vertical) Communication and controls talk to each other throughout the building
Test and balance Air flows and water flows match the design
Functional performance testing The systems work, and the commissioning agent tries to make them fail
Integrated systems testing Every system works together
Final acceptance testing The AHJ and the engineers accept the building

Coordinate Fire Alarm and Life Safety Testing

Functional performance testing has to be choreographed with fire alarm testing, because you have fire smoke dampers inside the HVAC system. You cannot pile them all on top of each other at the end. While test and balance and functional performance testing are happening, you will also be:

  • Tracking your elevators to completion, so you can get your state elevator inspection done.
  • Getting all of your fire sprinkler heads installed, inspected, and ready to go.
  • Scheduling your fire alarm testing floor by floor up the building, and for the entire structure.
  • Handling any other testing requirements on your project.

This might sound silly, but outside your elevators, you will typically have a fire alarm device or fire sprinkler that is not roughed in yet because the elevator is delayed. Watch those. Do not fall asleep on that.

I prefer to schedule all of this right at the end of finishes, in blocks, on a rhythm, and as early as possible based on when your milestones are available.

What Do You Need for Substantial Completion?

You finish the job by being able to say:

  • Fire sprinklers are signed off.
  • The ADA walk has been done.
  • The interim life safety or life safety walk has been done.
  • Fire alarm testing is 100 percent complete.
  • Functional performance testing is substantially done, and you have a preliminary balancing report.
  • Elevator testing is done.
  • Anything you need to do in your stairwells is done, with the right signage.

Then, at the end, you have a punch list, your engineer sign-offs, your preliminary balance report, your fire alarm system, all other life safety systems, and your elevators, all coming together.

Pull Plan It and Track the Interconnections

This whole orchestration needs to be done in a pull plan that ties everything in the building together. The main things you are tracking are milestones, milestones, milestones, and interconnections. The best leaders I know have a solid grasp of this, and they generally have it mapped out before the project even starts. It is also why commissioning is one of the two things people forget when they build a path to finish.

If you want to go deeper on keeping all of this flowing in the field, our book Takt Steering & Control walks through it.

So here is the challenge. Before your next project starts, map out whole building commissioning backward from substantial completion. List every milestone and every interconnection, from permanent power to final acceptance, and put them in a pull plan.

Bottom line: Whole building commissioning comes down to milestones and interconnections, so pull plan it backward from substantial completion and start it as early as your milestones allow.

If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.

Want your team trained on this? See our Last Planner® System and Takt training.

On we go.

Frequently Asked Questions

What is whole building commissioning?

It is the process of bringing every building system together at the end of the job, testing it, and getting it accepted, working back from substantial completion with a commissioning pull plan.

What do you need before you can commission a whole building?

Permanent power, ductwork and hydronic piping, a complete controls network connected floor to floor, IDF rooms with internet, and gas and other ancillary equipment.

What is the difference between test and balance and functional performance testing?

Test and balance makes sure air and water flows match the design. Functional performance testing checks that the systems work, while the commissioning agent tries to make them fail.

Why coordinate fire alarm testing with commissioning?

Because fire smoke dampers sit inside the HVAC system. If you pile fire alarm testing and functional performance testing on top of each other at the end, you will struggle.

What do you need for substantial completion?

Signed-off fire sprinklers, the ADA and life safety walks, complete fire alarm testing, substantially complete functional testing with a preliminary balancing report, and finished elevator testing.

People Also Read:
How to Fix a Project With No Schedule: The Real Method
Field Quality Checklists
How Buffers Work in Takt Planning
Mastering Commissioning: The Ultimate Scheduling Guide
How to Run a Commissioning Kickoff Meeting

If you want to learn more we have:

-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.

Share:

    Share Link