I want to share exactly how I would recover a failing construction project, as a step-by-step list. Unfortunately, I have had to recover projects in my career. A company kept asking me to do it, and none of those projects were mine. I did not oversee them or plan them. Eventually I said, I will do one more, and that is it. Great construction companies pivot to pre-planning projects and preventing the fix, rather than having to fix them. It is understandable if you have to do this every now and then, but never make it a habit.
Short answer: To recover a failing construction project, build the team and work through them, with outside help if you need it. Start with a forensic look at the reality on site against the six Lean cores, plus logistics. Name the problem or constraint. Choose the right recovery moves: write it into a buffer, isolate it, rezone, or hold stable. Then map out a path to finish. Never default to adding labor, overtime, or money.
Why Do Construction Projects Fail?
Projects either start wrong or go wrong.
- They start wrong when we do not follow the advice in How Big Things Get Done by Bent Flyvbjerg and Dan Gardner, and the project does not get everything it needs in pre-construction or before the phase.
- They go wrong when there is no multiplier leader at the helm (Multipliers by Liz Wiseman), when the team does not have the behaviors of a team (The Five Dysfunctions of a Team by Patrick Lencioni), and when there is no strenuous performance goal (Silos, Politics, and Turf Wars by Patrick Lencioni).
In other words, if it starts wrong, it is because of a lack of pre-planning. If it goes wrong, it is because the team is not synchronized and working together. Our book Elevating Pre-Construction Planning addresses this, and the First Planner System covers it in a course you can take on your way to work.
Three Ways Companies Respond
When a project starts failing, I have seen three different responses:
| Response | What happens |
|---|---|
| Refuse help | We are going to ride this off the cliff. This is the worst thing you can do. |
| Send in a hero | The hero gets all the credit, the team feels humiliated, and nobody learns anything. |
| Build the team and work through them | Outside help works through the people, and the team becomes famous. This is the one I recommend. |
On one project on the east side of the Phoenix metropolitan area, I was asked to come in and help. We reset the project, got it back on track, and finished right on time. That had nothing to do with me. It was because of the system. On another project, they said, we do not need your help. They finished four and a half months behind schedule, about $2.3 million in the red, half of the team quit, and they will never work with that owner again. It was an absolute tragedy.
One of the worst things you can say is that you do not need help, or that you do not like consultants or coaches. All of the best companies have help. But they work through their people to get it done. Everyone at Elevate, LeanTakt, and our associate partners works through the team.
Step 1: Understand the Reality on Site
The first thing is to understand what is actually going on. We need a forensic analysis. Look at the signs of a project in trouble:
- The bathrooms, the lunchroom, and site cleanliness.
- Morale, and what the foremen are saying.
- Turnover, and people in the wrong roles.
- Procurement and the overall schedule.
- A failing trade partner who is not being helped and supported.
- A lack of communication, collaboration, or a bad environment.
- Trade partners not being paid on time.
Then assess each of the six Lean cores, plus logistics, against the reality on site:
- Respect for people, nature, and resources.
- Stability and standardization. Is the job clean, safe, and organized, with visual standard work for each crew?
- One-piece process or progress flow.
- Flowing together on a Takt time and pull. Is every train of trades flowing on a Takt time, with resources and materials pulled in to meet it?
- Total participation and visual systems from everybody on the job.
- Quality and continuous improvement.
- Logistics. Our companion book, Elevating Construction Logistics, covers this.
So you are not guessing at the reality. You are checking it against the foundation of everything we do.
Step 2: Name the Problem or Constraint
Before you fix anything, name the problem or the constraint. Is the problem actually a bottleneck? Usually it will be. Understand that first.
Step 3: What Are the Most Common Recovery Moves?
Once you know the problem, name the recovery moves. There are 12, and actually 16, because we codified four more from Todd Zabelle’s book Built to Fail. Here are the four most common:
- Write it into a buffer. If you planned your project, use the buffer you built in.
- Isolate it. Can you isolate the geographical location, or the activity itself?
- Rezone. You can recover quite a bit by going to smaller zone sizes and picking up the pace. Smaller zones mean smaller batch sizes, which narrows your overall throughput time, so the phase goes faster.
- Hold stable. Double down on pull planning, lookahead planning, pre-construction meetings, weekly work planning, stability, respect, cleanliness, and safety. Hold the line, like the famous scenes in Braveheart and Gladiator.
What Should You Never Do to Recover a Project?
Never default to these. I call them the deadly six, and Brooks’s Law, from Fred Brooks in The Mythical Man-Month, explains why adding people to a late project makes it later:
- Adding labor.
- Adding crews.
- Working overtime.
- Bringing too many materials out to the zone.
- Rushing, pushing, and panicking.
- Throwing money at the problem.
Step 4: Map Out the Path to Finish
Instead, map out a path to finish. Create a path of critical flow based on recovery moves with a production mindset, and start to work your plan in a stable way. I wrote about how to do this in How to Fix a Project With No Schedule. You do not want a panicker on your project. You want the stable, boring, lock-everything-in approach.
I remember a general superintendent I really loved, who came to Arizona to take over a project in Tucson from another superintendent. He sent everybody home, stood on the balcony, and asked, how can I get flow back into this building? Then he brought the trades back to work in a flow. He said the first thing he reestablished was flow.
If you want a great book on this, read The Fixer. It is based on Calumet K, a book that is more than a century old. I rewrote it to modernize the language, removed outdated commentary, and added my own commentary. Honestly, it should be called The Stabilizer. A Pattern for Superintendents is another great one.
So here is the challenge. If a project of yours is starting to slip, do not wait for it to fail. Do the forensic analysis against the six Lean cores, name the constraint, and pick your recovery moves this week, working through your team.
Bottom line: To recover a failing construction project, work through the team, understand the reality, name the constraint, use the right recovery moves, and hold stable instead of throwing labor and money at it.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
Want your team trained on this? See our Last Planner® System and Takt training.
On we go.
Frequently Asked Questions
How do you recover a failing construction project?
Build the team and work through them, understand the reality on site, name the problem or constraint, choose the right recovery moves, and map out a path to finish.
Why do construction projects fail?
They start wrong from a lack of pre-planning, or they go wrong because there is no multiplier leader, no team behaviors, and no strenuous performance goal.
What are the most common recovery moves?
Write it into a buffer, isolate the location or activity, rezone into smaller zones, and hold stable by doubling down on planning, respect, cleanliness, and safety.
What should you never do when a project is behind?
Never default to adding labor or crews, working overtime, bringing out too many materials, rushing and panicking, or throwing money at the problem.
Should you bring in a hero to fix a failing project?
No. The hero gets the credit, the team feels humiliated, and nobody learns. Bring in help that works through the team.
People Also Read:
The Fastest Way to Stabilize a Chaotic Job Site
How to Fix a Project With No Schedule: The Real Method
How Buffers Work in Takt Planning
We’re 6 Months Behind: The 30-Day Recovery Plan
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.