We’re 6 Months Behind: The 30-Day Recovery Plan

30-day recovery plan: a construction team reviewing a time-by-location plan on the wall of a jobsite trailer
Read 8 min

If your project is six months behind, here is the 30-day recovery plan I would use to stabilize it, on any size job, all the way up to megaprojects. I hate that this happens to people, but it is real, and we need to do it right if it ever happens. As the saying goes, everybody has a plan until they get punched in the face, and no plan survives contact with the enemy. So we need a plan for when our plan goes sideways.

Short answer: A 30-day recovery plan has four stages. In days 1 to 7, stabilize the site with a 6S reset, the meeting system, and human systems. In days 8 to 14, diagnose: map the work by location, find the constraint, and fix procurement. In days 15 to 21, build one plan to finish that flows, including commissioning. In days 22 to 30, accelerate with cycle time, full kit, and smaller zones, and stay transparent with the owner.

A Student Housing Project Pulled Back From Months Late

There was a massive student housing project in the northeast of the country, with a really great superintendent and a really great company. They called and asked for help, and everybody who does well asks for help. They were trending three and a half months late, and maybe really four and a half, because even the most aggressive projection in their CPM schedule showed three and a half. We followed this system and pulled it back to within two weeks of finishing. The owner was so happy with the recovery effort that they did not charge liquidated damages, and those damages were really high. The point is that the project team bought into the system and supported it.

The 30-Day Recovery Plan at a Glance

Days Focus What happens
1 to 7 Stabilize 6S the site, start the meeting system, and set up the human systems
8 to 14 Diagnose Map by location, find the constraint, reorganize by geography, fix procurement
15 to 21 One plan that flows Build one plan to finish, go to the bottleneck, and plan commissioning
22 to 30 Accelerate Narrow cycle times, enforce full kit, and rezone to smaller zones

Days 1 to 7: Stabilize

Nothing is more important than stabilizing right away. In the first seven days, I would:

  • 6S the entire site: sort, straighten, shine, standardize, sustain, and safety.
  • Get the meeting system up and running.
  • Get all of the human systems running: bathrooms, lunch areas, and morning worker huddles.

On most projects, I would do this in 48 hours, but on a massive project site it might take seven days.

Days 8 to 14: Diagnose

By now, the project is running clean, everybody is safe and organized, deliveries are coming in logically, the meetings are starting to create flow, and we are winning over the workforce. So we are not doing nothing. But in days 8 to 14, we diagnose where we are:

  • Map everything out in a time-by-location format.
  • Find the constraint. Is there a massive bottleneck? Is it a geographical problem?
  • Reorganize the team by geography.
  • Stabilize procurement.

Procurement drives me crazy. I ask, how are you tracking procurement? Well, the trade partners do it, and we trust the trades. No. That is not how we do it. Get a procurement log, or get procurement on your production plan, right away.

Days 15 to 21: One Plan to Finish That Flows

Next, I want one plan to finish, and it has to flow. If you have trade stacking or trade burdening, zoning is how you get it to flow. I have written about how to build a plan to finish.

Why Should You Go to the Bottleneck?

Amateur supers go out and fight any old fire. The best supers go to the bottleneck. Ask:

  • Where is the slowest crew? Not because they are bad, but because they have the hardest work.
  • Where is the slowest zone?
  • What is the most limiting factor?

That is where you go, to your hot zones and your bottleneck trade, and really help remove the problem.

Why Is Commissioning Already Late?

I have never seen a commissioning effort that was on time. By the time a project is in recovery, commissioning is already at least six weeks too late. We have to move it forward. Create a path to finish for commissioning, loop in the commissioning agent, and work out your path to connect the systems to get to your preliminary balance report. It takes time to create that report, and you need it for substantial completion. I have written more about this in Whole Building Commissioning.

So during days 15 to 21, you are not only creating a solid production plan. You also have to get MEP commissioning into it. Our book Elevating Construction Commissioning for Project Teams covers this, and we have activity templates in the toolbox on our website.

Days 22 to 30: Accelerate

In the last stretch, there are three ways to accelerate:

  1. Narrow your end-zone cycle time. If you are missing your Takt time, can you add swing capacity, train better, set up the environment, prefabricate, or set up logistics so your cycle times narrow and you hit your durations?
  2. Focus on full kit. We do not start anything until we have full kit. A lot of times, teams do not go slowly because of the crew. They go slowly because we do not have an operating logistics system. You need logistics, line-side inventory, and full kit, pre-kitted, inspected, and brought onto the site on time.
  3. Rezone to smaller zone sizes. This is clearly laid out in our Takt Planning book and the Takt Production System audiobook.

Be Transparent With the Owner the Whole Way

By day 30 at the latest, have an honest plan that is stabilized. And be transparent with the owner all the way through, so they can be a partner with you on this. I have written about this in How to Rebuild the Owner Relationship.

Another project we recovered, here in Phoenix, did all of these things, finished on time, and the owner became a raving fan.

There Is No Instant Pudding

W. Edwards Deming said there is no instant pudding.

You cannot just pour in water, stir, and have pudding. These things take a little time. What you cannot do is try to do it alone, and you cannot bring in a hero. You have to follow the plan with the team.

Remember the stages of a team: forming, storming, norming, and performing. In a recovery, you have to form the team again, storm a little, norm by getting everybody rallied behind the goal, and then perform, when people follow the goal, not the leader. You could maybe use a hero in the first two stages, but you need someone who works through the team for norming and performing. If you want to go deeper on holding the plan in the field, see our book Takt Steering & Control.

So here is the challenge. If your project is behind, put this 30-day recovery plan on a calendar. Commit to stabilizing in the first week, and tell your team and your owner exactly what happens in each stage.

Bottom line: In 30 days you can stabilize, diagnose, build one plan that flows, and start accelerating, as long as you work through the team instead of sending in a hero.

If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.

Want your team trained on this? See our Last Planner® System and Takt training.

On we go.

Frequently Asked Questions

What is a 30-day recovery plan in construction?

It is four stages: stabilize in days 1 to 7, diagnose in days 8 to 14, build one plan to finish that flows in days 15 to 21, and accelerate in days 22 to 30.

What should you do first when a project is months behind?

Stabilize. 6S the whole site, start the meeting system, and set up the human systems like bathrooms, lunch areas, and morning worker huddles.

Why should a superintendent go to the bottleneck?

Because the bottleneck limits the whole job. Amateurs fight any old fire, but the best supers go to the slowest crew, the slowest zone, and the most limiting factor.

Why does commissioning matter in a recovery?

By the time a project is in recovery, commissioning is usually already late. You need a path to finish for commissioning, including the preliminary balance report you need for substantial completion.

How do you accelerate a project without overtime?

Narrow your cycle times with swing capacity, training, prefabrication, and logistics, enforce full kit before starting work, and rezone to smaller zone sizes.

People Also Read:
How to Recover a Failing Construction Project
The Fastest Way to Stabilize a Chaotic Job Site
What Is 5S and How It Applies to Construction

If you want to learn more we have:

-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)

Discover Jason’s Expertise:

Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.