Here’s the deal. If your project is three months behind, you have to do something about it. Here is the step-by-step recovery plan I use, and it is quite remarkable. It works in three columns: the path of critical flow, the constraints, and the opportunities for recovery.
Short answer: If your project is three months behind, map a complete path of critical flow first, including site work and commissioning, so you can see exactly how far behind you are. Then map every known constraint phase by phase. Look for optimization strategies, like isolating, resequencing, rezoning, or designing to the work package, and work through each opportunity line by line. Get the owner on board, issue zero change orders, and never fall back on the seven deadly sins.
| Column 1 | Column 2 | Column 3 |
|---|---|---|
| Path of critical flow | Constraints | Opportunities for recovery |
| Map the complete plan and see how far behind you are | List every known constraint, phase by phase | Talk through each one, line by line, and keep what is realistic |
Step 1: Review Your Production Plan and Map the Path of Critical Flow
First, look at your existing production plan and make sure it is complete. I cannot stress that enough. Almost every production plan I analyze is incomplete for site work and commissioning. I have written about commissioning in Whole Building Commissioning.
Then map out the path of critical flow, and show exactly how far behind you actually are.
What Is the Difference Between the Critical Path and the Path of Critical Flow?
The path of critical flow includes your activities, durations, sequence, logic ties, trade flow, and buffers. The critical path only has the first four, which is very problematic.
All Lean systems are seeing systems, and you can only see this properly in a Takt plan. You cannot see it in CPM. I can’t believe CPM is still around. If you want to know why, read our book The 10 Myths of CPM.
Step 2: Map Out All Known Constraints
Now take that plan and map out every known constraint. That is why you have to see it visually. Our full list of visual constraint signage and boards is in our book Takt Steering & Control and in the toolbox on our website.
In each phase, the typical constraints are:
- Improper Takt time.
- Improper sequence.
- Improper zone size.
- Improper zone leveling.
- Improper activity leveling.
- Not recognizing the actual physical constraints.
I could keep going, but they are all system problems. Go through your path of critical flow phase by phase: I do not have enough zones here. I need to prefabricate something here. List all of the constraints, meaning all of the problems or bottlenecks in your plan.
Step 3: Look for Optimization Strategies
Once you have mapped the constraints, you will know what optimization strategies are available to you. The most common ones I love are:
- Isolate the problem.
- Resequence around the problem.
- Rezone around the problem.
- Design to the work package.
They are all listed in our books Takt Planning and Takt Steering & Control, and in the Takt Production System audiobook.
Why Aren’t All Recovery Opportunities Realistic?
Not all of those strategies will be available. When we are asked to analyze and peer review megaprojects, not all of our suggestions are realistic either. So each constraint goes into your third column: opportunities for recovery.
Each one could save weeks or months on its own. But each one is a conversation. No, this one is not possible. Oh yes, but we could do that. That one is not possible, but it gives me five more ideas. Go line item by line item, dig deeper, and really map the recovery out, so your new path of critical flow shows a clear path to recover the project.
Step 4: Implement the Recovery
Now you have to implement it and take the physical steps to get it done:
- Make sure you have a path to finish.
- Get the owner on board. I have written about this in How to Rebuild the Owner Relationship.
- Issue zero change orders.
- Rein in the supply chain.
- Engage in the field.
What Are the Seven Deadly Sins of Recovery?
Here is what I would never do again. I call these the seven deadly sins of recovery:
- Just adding labor.
- Adding crews.
- Working overtime.
- Thinking of Saturday as a buffer.
- Throwing money at the problem.
- Bringing out too many materials.
- Rushing, pushing, and panicking.
Instead, I enable flow by constantly removing roadblocks and optimizing constraints. In the Takt Production System, there are 12 opportunities to recover, and four more beyond that which are quite advanced. There is no need to shorten the trades’ durations, and there is no need to commit the seven deadly sins. I have written more on recovery in How to Recover a Failing Construction Project.
So here is the challenge. If your project is three months behind, build the three columns this week: your path of critical flow, your constraints, and your opportunities for recovery. Then sit down with your team and go line by line.
Bottom line: When you are three months behind, map the path of critical flow, list every constraint, work through realistic recovery opportunities line by line, and never fall back on the seven deadly sins.
If your project needs superintendent coaching, project support, or leadership development, Elevate Construction can help your field teams stabilize, schedule, and flow.
Want your team trained on this? See our Last Planner® System and Takt training.
On we go.
Frequently Asked Questions
What should you do if your project is three months behind?
Map a complete path of critical flow, list every known constraint, find realistic opportunities for recovery line by line, get the owner on board, and enable flow by removing roadblocks.
What is the path of critical flow?
It includes your activities, durations, sequence, logic ties, trade flow, and buffers. The critical path only has the first four.
What are the most common schedule recovery strategies?
Isolate the problem, resequence around it, rezone around it, or design to the work package.
What are the seven deadly sins of schedule recovery?
Adding labor, adding crews, working overtime, treating Saturday as a buffer, throwing money at the problem, bringing out too many materials, and rushing, pushing, and panicking.
Do you need to shorten trade durations to recover a schedule?
No. In the Takt Production System, there are 12 opportunities to recover and four advanced ones, without shortening trade durations.
People Also Read:
We’re 6 Months Behind: The 30-Day Recovery Plan
How to Recover a Failing Construction Project
How Buffers Work in Takt Planning
If you want to learn more we have:
-Takt Virtual Training: (Takt Virtual Training)
-Check out our YouTube channel for more info: (Elevate Construction on YouTube)
-Listen to the Elevate Construction podcast: (Elevate Construction Podcast)
-Check out our training programs and certifications: (Training Programs and Certifications)
-The Takt Book: (The Takt Book on Amazon)
Discover Jason’s Expertise:
Meet Jason Schroeder, the driving force behind Elevate Construction. As the company’s Founder and COO, he’s dedicated to taking construction to new heights. With a wealth of industry experience, he’s crafted the Field Engineer Boot Camp and Superintendent Boot Camp – intensive training programs engineered to cultivate top-tier leaders capable of steering their teams towards success. Jason’s vision? To expand his training initiatives across the nation, empowering construction firms to soar to unprecedented levels of excellence.